== <font color=blue>''' Run Plan:'''</font>== | == <font color=blue>''' Run Plan:'''</font>== | ||
− | |||
* When the beam tune is acceptable in the upstream beamline, turn off/degauss the tagger magnet and tune 10 nA beam to the Faraday Cup. The beamline expert (Stepan) will oversee this work remotely. As part of the beam tuning, bring the solenoid magnet to 100% field. (Contact the PDL (Eugene) to change the magnet settings - only authorized personnel can change the field settings) | * When the beam tune is acceptable in the upstream beamline, turn off/degauss the tagger magnet and tune 10 nA beam to the Faraday Cup. The beamline expert (Stepan) will oversee this work remotely. As part of the beam tuning, bring the solenoid magnet to 100% field. (Contact the PDL (Eugene) to change the magnet settings - only authorized personnel can change the field settings) | ||
** After both magnets are at full field, record in the logbook the screens for the load cells and strain gauges for the torus and the screens for the load cells and EM forces for the solenoid. | ** After both magnets are at full field, record in the logbook the screens for the load cells and strain gauges for the torus and the screens for the load cells and EM forces for the solenoid. |
Revision as of 07:30, 17 January 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Winter 2018
Beam energy 2.1 GeV (1 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Daniel S. Carman
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 2: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". The DAQ rate should be 2 -3 kHz (this includes a 1 kHz pulser). After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 3: Nominal beam positions: 2C21 (X=-0.2 mm, Y=-0.2 mm), 2C24 (X=-0.5 mm, Y=0.9 mm), 2H01 (X=0.5 mm, Y=1.5 mm)
Run Plan:
Beam Tuning:
When ready to get beam, turn all beamline devices ON, turn all CLAS12 detectors OFF |
General Instructions:
Every Shift:
Every Run:
|
Webcams |
Manuals |
Epics on the web
|