Line 115: | Line 115: | ||
* Zero field alignment runs: | * Zero field alignment runs: | ||
** Starting at 8:00 am, ramp the torus to 0 field (call E. Pasuyk and/or RC to do it) | ** Starting at 8:00 am, ramp the torus to 0 field (call E. Pasuyk and/or RC to do it) | ||
+ | ** Empty the target | ||
** Establish a beam current of 0.1 nA and start the DAQ with electron trigger | ** Establish a beam current of 0.1 nA and start the DAQ with electron trigger | ||
** Start lowering the solenoid in steps of 10% while monitoring detectors rates (call detector experts and SVT and MVT in particular ahead of time to have them watching their system) and DC occupancies. At 40% solenoid, ask MCC to mask the solenoid relay from the FSD. Continue ramping down the solenoid until rates are sustainable. | ** Start lowering the solenoid in steps of 10% while monitoring detectors rates (call detector experts and SVT and MVT in particular ahead of time to have them watching their system) and DC occupancies. At 40% solenoid, ask MCC to mask the solenoid relay from the FSD. Continue ramping down the solenoid until rates are sustainable. |
Revision as of 17:38, 19 January 2018
[edit]
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Winter 2018
Beam energy 2.1 GeV (1 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: Raffaella De Vita
- (757) 575-7540
- 9 575 7540 from Counting Room
- carman@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
- Note 1: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
- Note 2: At the end of each run, follow the DAQ restart sequence "end run", "abort", "reset", "download", "prestart", "go". The DAQ rate should be 5 - 6 kHz (this includes a 1 kHz pulser). After DAQ prestart is complete reboot the scaler IOCs with the command: iocjscalerRestartAll.sh. Note: After each step, make sure it is complete in the Run Control message window. If a roc has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 3: Nominal beam positions: 2C21 (X=0.0 mm, Y=0.0 mm), 2C24 (X=0.0 mm, Y=0.7 mm), 2H01 (X=1.0 mm, Y=-1.0 mm)
Run Plan:(last update 1/19 - 4:30 pm)
Beam Tuning:
When ready to get beam, turn all beamline devices ON, turn all CLAS12 detectors OFF |
General Instructions:
Every Shift:
Every Run:
|
Webcams |