Engineering Run
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals |
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Engineering Run, Fall 2017
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!
RC: Raffaella DeVita
- (757) 575-7540
- 9 575 7540 from Counting Room
- devita@jlab.org
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
- pasyuk@jlab.org
Run Plan: beamline commissioning
for dumping the beam in the designated dump on the tagger yoke. MCC will ask you to change (set) the beam delivery mode.
long Ni cylinder, without a hole)
deliver beam to the tagger yoke dump (<=5 nA). It may take ~1 hour for MCC to setup and cleanly transport beam to the tagger yoke dump,
to retune if needed (e.g. beam is too wide or asymmetric or has large tails), repeat the scan after every tune. Iterate to get acceptable beam profile.
its max, torus is at 100%.
the downstream viewer in beam position (if it is not already)
Important Notes:
|
General Instructions:Locking up the hall
|
Every Shift:
|
Every Run:
|
---|