The beam test will use a GEM detector and a small calorimeter behind one arm of the pair spectrometer in Hall-D. The setup will use two FPGA's, one for each detector, to process triggered data from the DAQ and send it into a JANA2 process. The downstream JANA2 process will run some algorithm on the data (proof-of-principle) and write the output to a file.
Meetings
Project Phases
Phase 1:
- Single detector readout (calorimeter)
- CDAQ, no FPGA
- JANA2 JStreamingEventSource with direct reading of TCP socket
Phase 2:
- Single detector readout (calorimeter)
- CDAQ, with FPGA
- JANA2 JStreamingEventSource with direct reading of TCP socket
Phase 3:
- Two detector readout
- CDAQ, with FPGA
- JANA2 JStreamingEventSource with direct reading of TCP socket, simple event building
Phase 4:
- Two detector readout
- CDAQ, with FPGA
- ERSAP backend with event building
- JANA2 algorithm
- ERSAP Event Recorder
Timetable of Activities
Activity | start date | end date | |
---|---|---|---|
step 1: | switch to cDAQ | 2/6 | 2/8 |
step 2: | build events in cDAQ and send to Jana. | 2/9 | 2/14 |
step 3: | TCP interface in FPGA (low speed - 1GB) and build events in FPGA | 2/14 | 2/22 |
step 4: | send events from FPGA to Jana; | 2/23 | 2/27 |
step 5: | work on NN processing in FPGA. | 2/27 | 3/13 |
step 6: | send from FPGA to Jana : original and processed; | 3/13 | 3/14 |
step 7: | continue work on ML FPGA algorithms and test new FPGA boards. | 3/14 | 3/20 |
Capability Focus | start date | end date |
---|---|---|
JANA2 plugins - TriDAS | 2/6 | 2/10 |
JANA2 plugins - CDAQ | 2/13 | 2/17 |
CDAQ + JANA2 | 2/20 | 2/24 |
TriDAS + JANA2 | 2/27 | 3/3 |
ERSAP + TriDAS | 3/6 | 3/10 |
ERSAP + CDAQ | 3/13 | 3/17 |
Accelerator Down | 3/20 |