This is information related to beam tests done in support of the ML-FPGA R&D for EIC project.

Overview

The beam test will use a GEM detector and a small calorimeter behind one arm of the pair spectrometer in Hall-D. The setup will use two FPGA's, one for each detector, to process triggered data from the DAQ and send it into a JANA2 process. The downstream JANA2 process will run some algorithm on the data (proof-of-principle) and write the output to a file.


Meetings

Project Phases

Phase 1:

  • Single detector readout (calorimeter)
  • CDAQ, no FPGA
  • JANA2 JStreamingEventSource with direct reading of TCP socket

Phase 2:

  • Single detector readout (calorimeter)
  • CDAQ, with FPGA
  • JANA2 JStreamingEventSource with direct reading of TCP socket

Phase 3:

  • Two detector readout
  • CDAQ, with FPGA
  • JANA2 JStreamingEventSource with direct reading of TCP socket, simple event building

Phase 4:

  • Two detector readout
  • CDAQ, with FPGA
  • ERSAP backend with event building
  • JANA2 algorithm
  • ERSAP Event Recorder

Timetable of Activities

Activity start date end date
step 1: switch to cDAQ 2/6 2/8
step 2: build events in cDAQ and send to Jana. 2/9 2/14
step 3: TCP interface in FPGA (low speed - 1GB) and build events in FPGA 2/14 2/22
step 4: send events from FPGA to Jana; 2/23 2/27
step 5: work on NN processing in FPGA. 2/27 3/13
step 6: send from FPGA to Jana : original and processed; 3/13 3/14
step 7: continue work on ML FPGA algorithms and test new FPGA boards. 3/14 3/20


EPSCI SRO Beam test priority Schedule
Capability Focus start date end date
JANA2 plugins - TriDAS 2/6 2/10
JANA2 plugins - CDAQ 2/13 2/17
CDAQ + JANA2 2/20 2/24
TriDAS + JANA2 2/27 3/3
ERSAP + TriDAS 3/6 3/10
ERSAP + CDAQ 3/13 3/17
Accelerator Down 3/20