+ | ==Every Shift:== | ||
+ | # Follow run plan as outlined by RC | ||
+ | # If any concern about beam stability, ask MCC if orbit locks are on (they should be). | ||
+ | # Keep shift summary up to date in HBLOG. Record all that happens. | ||
+ | #* Check on white board all scalers, strip charts and monitoring plots that need to be logged regularly | ||
+ | #* Document any beam condition change and send scaler GUIs to HBLOG | ||
+ | #* [https://bta.acc.jlab.org Fill out BTA] hourly. Click "Load from EPICS" to automatically fill the left side. | ||
+ | #* Fill and submit the [https://logbooks.jlab.org/checklists/151 shift checklist in the logbook] | ||
+ | # Perform 2H02A harp scan once per shift or when beam conditions have changed, based on beam monitors (BPMs, halo rates, beam-viewer). During harp scans SVT must be retracted and HV should be OFF. | ||
+ | # '''With any issue contact On-Call Experts or RC''' | ||
=== Important Notes: === | === Important Notes: === |
Revision as of 19:13, 24 June 2019
[edit]
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2019,2016, 2015HPS Upgrade ERRCOO, ESAD, RSAD Things to read before shift. |
Procedures
|
Manuals |
JLab Logbooks
|
HPS 2019 run, June X to August Y'
Beam energy 4.5 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 2pm
RC: Matt Graham
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Valery Kubarovsky
- (757) 876-1789
- 9 876-1789 from Counting Room
* !! Chicane magnets can be energized only when the hall is in Beam Permit, [1]. Chicane magnets must be off if the hall is in Restricted or in Controlled access.
Run Plan June 20 - 21, 2019
When there is stable beam:
Every Shift:
Important Notes:
|
General InstructionsEstablishing Physics Quality Beam for HPS:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
RC daily meetings at 2 pm in the counting-house 2nd-floor conference room.
BlueJeans Info:
URL: https://bluejeans.com/794825703
Meeting ID: 794825703
|
|
|
Webcams:
|
Accelerator:
|
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 310-7198 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |