Line 140: | Line 140: | ||
#* Target: 4 microns W | #* Target: 4 microns W | ||
#* Current: 30 nA | #* Current: 30 nA | ||
+ | # v6 NoHodoTET | ||
+ | #* Beam current 100 nA, or as high as SVT experts will agree on. | ||
+ | #* Configuration: PROD66 | ||
+ | #* Take 15M events with hps_v6_NoHodoTET.trg | ||
+ | #* This is the same as the v6. with only difference that only for Hodo channels TET is set to 0. | ||
+ | #* This run will allow to choose TET values for Hodoscope | ||
# v6 run | # v6 run | ||
#* Configuration: PROD66 | #* Configuration: PROD66 |
Revision as of 01:34, 18 July 2019
[edit]
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2019,2016, 2015HPS Upgrade ERRCOO, ESAD, RSAD Things to read before shift. |
Procedures
|
Manuals |
JLab Logbooks
|
HPS (E12-11-006) 2019 run, June X to August Y'
Beam energy 4.5 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 2pm
RC: Rafayel Paremuzyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Valery Kubarovsky
- (757) 876-1789
- 9 876-1789 from Counting Room
* !! Chicane magnets can be energized only when the hall is in Beam Permit, [1]. Chicane magnets must be off if the hall is in Restricted or in Controlled access.
* Fill out BTA hourly. Click "Load from EPICS" to automatically fill the left side then make sure numbers are correct. If needed edit the entry. NO ABUs or BANU if beam tune is in progress, make it all BNA with ER 100%.
Run Plan July 17-18, 2019Hot items:
Schedule and plans:
Every Shift:
Every Run:
Important Notes:
|
General InstructionsEstablishing Physics Quality Beam for HPS:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
|
|
---|
RC daily meetings at 2 pm in the counting-house 2nd-floor conference room.
BlueJeans Info:
URL: https://bluejeans.com/794825703
Meeting ID: 794825703
|
|
|
Webcams:
|
Accelerator:
|
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 310-7198 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |