=== Bringing beam to the hall: ===
+
=== Bringing beam to the hall (consult with RC with any problem): ===
 
# First beam comes to tagger dump. Ask MCC to turn on tagger magnet, check that beam type is "photon"
 
# First beam comes to tagger dump. Ask MCC to turn on tagger magnet, check that beam type is "photon"
# Follow instructions under "Procedures" on the documentation wiki for "Beamline" to establish beam to the tagger dump first  
+
# Follow instructions under "Procedures" on the documentation tab for "Beamline" to establish beam to the tagger dump first.
# Make sure nA BPMs will be calibrated while running beam to the tagger dump (depends on time of day when beam will be available for BPM calibration, consult with RC).
+
# Make sure nA BPMs are calibrated while running beam to the tagger dump (this depends on time of day when beam will be available for BPM calibration).
# <b> After reasonable beam will be established on the tagger dump </b>
+
# <b> After reasonable beam is established on the tagger dump ask MCC to degauss the tagger magnet and deliver beam to the Hall-B electron dump (to Faraday cup). For "reasonable" see "Acceptable Beam Conditions" on the right column of this page, not much is changed in beam optics from the previous run, beam profile at 2C21 should be < 0.1 mm and < 0.4 mm on 2C24 (tagger) harps, both X and Y.</b>
 +
# Follow the instructions under "Procedures" on the documentation tab for "Beamline" to establish beam to the electron dump. If needed move SVT protection collimator up/down (motion should not be more than a 1mm
 
<!-- #* Check if DAQ runs properly and if all monitors look reasonable on both SVT and ECal (call experts)
 
<!-- #* Check if DAQ runs properly and if all monitors look reasonable on both SVT and ECal (call experts)
 
#* Log errors for each DAQ crash
 
#* Log errors for each DAQ crash

Revision as of 10:10, 4 February 2016


[edit]
HPS 2016 run, February 4 to March 14, weekends only.
Shifts are manned from Friday 12pm to 7am on Monday.
Beam energy 2.3 GeV (1 pass).
Important: Document all your work in the logbook!

RC: Stepan Stepanyan

  • (757) 575-7540
  • 9 575 7540 from Counting Room

PDL: Harut Avagyan

Run Plan for February 5 - 7, 2015:

Locking up the hall

  • At noon (Friday), check the status of hall work and notify RC if there are delays for lockup. Work with RC to make sure that hall is ready for sweep at 1pm.
  • Make sure experts, beamline, ECal, SVT, and slow controls, checked their systems, and that all clear for lockup.
  • Make sure all necessary monitoring GUIs are up and running.
  • Make sure beam viewer screens are up


Bringing beam to the hall (consult with RC with any problem):

  1. First beam comes to tagger dump. Ask MCC to turn on tagger magnet, check that beam type is "photon"
  2. Follow instructions under "Procedures" on the documentation tab for "Beamline" to establish beam to the tagger dump first.
  3. Make sure nA BPMs are calibrated while running beam to the tagger dump (this depends on time of day when beam will be available for BPM calibration).
  4. After reasonable beam is established on the tagger dump ask MCC to degauss the tagger magnet and deliver beam to the Hall-B electron dump (to Faraday cup). For "reasonable" see "Acceptable Beam Conditions" on the right column of this page, not much is changed in beam optics from the previous run, beam profile at 2C21 should be < 0.1 mm and < 0.4 mm on 2C24 (tagger) harps, both X and Y.
  5. Follow the instructions under "Procedures" on the documentation tab for "Beamline" to establish beam to the electron dump. If needed move SVT protection collimator up/down (motion should not be more than a 1mm

Miscellaneous Notes:

  1. If you change beam current, turn orbit locks off first, there is a current - position dependence on the stripline BPMs 2H00 and 2H02
  2. Do NOT change chicane magnet currents when beam is on
  3. Do not run more than 30 minutes above 50 nA without the beam blocker in front of Faraday cup. Put beam blocker in for long running at high currents.


General Instructions:

Recovering from beam trips when running SVT at 0.5 mm:

  1. SVT HV will trip off automatically
  2. Check the FSD GUI to see if high rates in the HPS halo counters generated the trip
    • If it was not an HPS halo counter trip, MCC will restore the beam as usual (following their own instructions). As soon beam is back and stable, restore SVT HV.
    • If it was an HPS halo counter trip, MCC will not restore the beam. Inform MCC that we will get back to them when we are ready for beam.
      1. Retract the SVT to its 1.5 mm stations, both top and bottom.
      2. Tell MCC we are ready for beam.
      3. Once beam is restored, confirm that both 2H02 beam positions x and y are as desired and halo counter rates are as expected.
      4. Once beam is stable for ~1 minute, restore SVT HV and the SVT to its nominal position.
      5. Resume data taking.

Every Shift:

  1. Follow run plan as outlined by RC
  2. If any concern about beam stability, ask MCC if orbit locks are on (they should be).
  3. Keep shift summary up to date in HBLOG. Record all that happens.
    • Check on white board all scalers, strip charts and monitoring plots that need to be logged regularly
    • Document any beam condition change and send scaler GUIs to HBLOG
    • Fill and submit the shift checklist in the logbook
  4. Perform 2H02A harp scan once per shift or when beam conditions have changed, based on beam monitors (BPMs, halo rates, beam-viewer)
  5. With any issue contact On-Call Experts or RC

Every Run:

  1. After "Prestart" but before "Go", Check ECal Latency
  2. After "Go": Check SVT Occupancy
  3. Update the run spreadsheet on Google Docs.
  4. See the whiteboard for everything else that should be done on a per-run basis.

Setting up Chicane for E=2.3 GeV:

Note: This requires Beam Permit and NO beam to HPS / Faraday Cup.

  1. Turn on chicane power supplies following instructions on the documentation page on Turning Chicane ON/OFF

SVT Instructions:

  1. Turn SVT completely OFF (Bias, FEB, Flange) when entering Beam Permit.
  2. Before sending beam to Faraday cup, verify (and page SVT expert if otherwise):
    • SVT should be open: "Position" at 0.000 mm in the main scaler_hps GUI
    • SVT HV is off: all red/green indicators RED in SVT bias GUI
  3. The first time sending beam to the Faraday cup after the hall is closed, page the SVT expert.

ECAL Instructions:

  • HV must be OFF during FIRST delivery of beam to the Faraday Cup after tuning to the Tagger Dump.
    • Only after stable beam established to Faraday Cup can HV can be turned ON.
  • HV should be OFF when running beam studies with Struck scalers with 1 mm wire or tuning collimator position.

Acceptable Beam Conditions:

  1. To establish good beam conditions
    1. Make sure SVT is completely OFF (see above)
    2. First send beam to the tagger dump (ask MCC to turn ON the tagger), meanwhile turn on the Chicane (see above)
    3. Check the beam position on the tagger viewer, it should be approximately in the center of the screen
    4. Check profile using 2C21 and tagger harp scans, and compare the positions and widths with previous scans ([1],[2]). Positions on both harps should be with +/- 1mm, widths on 2C21 shoud be ~0.05 within 0.05 mm, and on the tagger harp ~0.35mm within 0.1mm.
    5. Halo counters TAG-L/T/T2 should be ~10Hz/nA [3]
  2. While MCC degausses the tagger magnet, verify that chicane is ON
    • If not, turn it on. Strictly follow the procedure in the beam line manual!
  3. Before sending beam to the Faraday cup
    • Check 3mm collimator is IN
    • Check HPS target is OUT
    • Check SVT is OUT (position 0 mm)
    • Check ECal HV is OFF
  4. Send beam to the Faraday cup
    • Ask MCC to establish 25 nA beam with HPS orbit locks on (We need HallBHPSOrb not HallBOrb configuration)
    • Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [4])
    • Check the beam spot on chromax viewer
    • The halo counter rates before HPS must be low:
      1. UPS-L and UPS-R few Hz/nA,
      2. The tagger counters should count less than Hz/nA and downstream counters should count ~Hz/nA
      3. The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 100 Hz/nA [5]
    • Positions on BPMs must be close to what they were before [6]
    • Insert the 4um W target without turning off the beam.
  5. Before accepting beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI.


Run Coordinator
Feb 3 - Feb 10 Stepan Stepanyan
Feb 10 - Feb 17 Takashi Maruyama
Feb 17 - Feb 24 John Jaros
Feb 24 - Mar 2 Raphaël Dupré
Mar 2 - Mar 9 Nathan Baltzell
Mar 9 - Mar 16 Maurik Holtrop
Physics Division Liaison
Feb 3 - Mar 16 Harut Avagyan
Beamline
Feb 4 - Feb 10 F.X. Girod
Feb 10 - Feb 17 Stepan Stepanyan
Feb 17 - Feb 24 Rafo Paremuzyan
Feb 24 - Mar 2 Clive Field
Mar 2 - Mar 9 Takashi Maruyama
Mar 9 - Mar 16 John Jaros
SlowControls
Feb 4 - Feb 11 Stepan Stepanyan
Feb 12 - Feb 18 Sho Uemura
Feb 19 - Feb 25 Bryan McKinnon
Feb 26 - Mar 10 Hovanes Egiyan
Mar 11 - Mar 14 Nathan Baltzell
ECAL
Feb 2 - Feb 9 Holly Vance
Feb 9 - Feb 16 Nathan Baltzell
Feb 16 - Feb 23 Raphaël Dupré
Feb 23 - Mar 1 Andrea Celentano
Mar 1 - Mar 8 Gabriel Charles
Mar 8 - Mar 15 Gabriel Charles
SVT
Feb 4 - Feb 12 Matt Graham
Feb 12 - Feb 19 Sho Uemura
Feb 19 - Feb 26 Matt Solt
Feb 26 - Mar 4 Vitaliy Fadeyev
Mar 4 - Mar 14 Tim Nelson
DAQ
Feb 3 - Mar 16 Sergey Boyarinov



Spring 2015 Final @ 1 GeV:

.

Charge.png


System/Person Pager/Phone Number
Run Coordinator (757) 575-7540 (cell)
Physics Div. Liaison (757) 876-1789 (cell)
MCC-OPS 7048
Crew Chief 7045
Crew Chief 9-879-3367 (cell)
Program Deputy 9-876-7997 (cell)
Gate House Guard 5822
DAQ/Online (757) 869-2188 (cell)
SVT (757) 541-7539 (cell)
ECAL (757) 810-1489 (cell)
Slow Controls (757) 748-6922 (cell)
Beamline (757) 303-3996 (cell)
Engineering (757) 748-5048
Hall-B Floor 5165
Hall-B Space Frame 5170, 5171
Hall-B Forward Carriage 5371
Hall-B Counting Room 5126, 5244, 5246, 5247
Hall-B Gas Shed 7115


Svtpic.png

Ecalpic.png