Line 110: | Line 110: | ||
# The required beam profile at 2H02A harp is: X-width <~0.25 mm, Y-width <~ 0.10 mm, and the tilt angle <15 degrees. The spot on the Chromax viewer should be close to x=-2mm, y=-5mm. <b> Do not waste too much time on the initial beam tune, as long as rates on the halo counters are low - Downstream L/R/T/B and HPS-L/R <~few Hz/nA, and HP-SC < few x 10 Hz, the following program still can be done:</b> | # The required beam profile at 2H02A harp is: X-width <~0.25 mm, Y-width <~ 0.10 mm, and the tilt angle <15 degrees. The spot on the Chromax viewer should be close to x=-2mm, y=-5mm. <b> Do not waste too much time on the initial beam tune, as long as rates on the halo counters are low - Downstream L/R/T/B and HPS-L/R <~few Hz/nA, and HP-SC < few x 10 Hz, the following program still can be done:</b> | ||
# SVT Expert resets beam position with SVT wire scan. | # SVT Expert resets beam position with SVT wire scan. | ||
− | #* run svt wire scan | + | #* run svt wire scan. See https://logbooks.jlab.org/entry/3379399 |
− | #* have MCC move beam to x=0.0, y=0.0 mm using upstream correctors and Frascati current. | + | #* have MCC move beam to x=0.0, y=0.0 mm using upstream correctors and Frascati current.If need to move to beam's right,subtract 10A from Frascati (1 mm), rest with correctors. If need to move to beam's left, split the difference between Frascati (add 10A/mm) and corrector. See that Chromax spot hasn't moved too far and confirm with SVT wires. |
− | |||
#* repeat and record 2H02 harp scan and BPM values. These are the new standards. | #* repeat and record 2H02 harp scan and BPM values. These are the new standards. | ||
− | #* repeat scan of the 2.25 mm collimator and re-center it. Record the new position have it entered into the epics data base. | + | #* repeat scan of the 2.25 mm collimator and re-center it. Record the new position have it entered into the epics data base.See https://logbooks.jlab.org/entry/3379405 |
# Restore ECal and Trigger | # Restore ECal and Trigger | ||
#* turn on ECal | #* turn on ECal | ||
#* ECal Expert measures pedestals | #* ECal Expert measures pedestals | ||
− | #* Record FADC rates with and without the 4 um target at 100 nA, then 200 nA. Agree with last weekend? | + | #* Record FADC rates with and without the 4 um target at 100 nA, then 200 nA. Agree with last weekend? See https://logbooks.jlab.org/entry/3379417 |
#* Trigger rate studies (see instructions under "procedures" for trigger on wiki) | #* Trigger rate studies (see instructions under "procedures" for trigger on wiki) | ||
#* Trigger/DAQ expert checks trigger rates, DAQ, and deadtime with 200 nA beam on 4 um target. Record: | #* Trigger/DAQ expert checks trigger rates, DAQ, and deadtime with 200 nA beam on 4 um target. Record: | ||
Line 127: | Line 126: | ||
--> | --> | ||
# SVT Expert program at 1.5 mm (shifters run beam stability checks in parallel--see below) | # SVT Expert program at 1.5 mm (shifters run beam stability checks in parallel--see below) | ||
− | #* Ensure that BPM 2H02 is stable and FSD system is on | + | #* Ensure that BPM 2H02 is stable and FSD system is set properly for 200 nA and on. |
#* Turn on SVT | #* Turn on SVT | ||
#* Move to 1.5 mm | #* Move to 1.5 mm | ||
Line 135: | Line 134: | ||
#* Plot and record halo rate histories and BPM 2H02 histories | #* Plot and record halo rate histories and BPM 2H02 histories | ||
#* Does beam move at time of trips? How stable is beam in x and y? | #* Does beam move at time of trips? How stable is beam in x and y? | ||
− | #* Which trips are initiated by FSD? | + | #* Which trips are initiated by FSD? See FSD GUI. |
# SVT Commissioning | # SVT Commissioning | ||
#* If beams are stable, SVT expert moves SVT to 1.0 and then 0.5 mm | #* If beams are stable, SVT expert moves SVT to 1.0 and then 0.5 mm | ||
Line 146: | Line 145: | ||
#* Include 1 hour of FEE trigger | #* Include 1 hour of FEE trigger | ||
#* Bulk of data with Pairs1 trigger | #* Bulk of data with Pairs1 trigger | ||
− | #* If get several hours worth of data, and it's not too late ( | + | #* If get several hours worth of data, and it's not too late (> 8PM), call Mike Tiefenbach (if Sunday) or Arne Freyberger (if, miraculously, it's Saturday) to do improve vertical beam size. |
#* If it's too late, take data. | #* If it's too late, take data. | ||
Revision as of 17:58, 19 February 2016
[edit]
HPS 2016 run, February 4 to March 14, weekends only.
Shifts are manned from Friday 3pm to 7am on Monday.
Beam energy 2.3 GeV (1 pass).
Important: Document all your work in the logbook!
Spring 2015 Final @ 1 GeV:
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2016, 2015 |
Procedures
|
Manuals |
JLab Logbooks
|
RC: John Jaros (Bluejeans info for Run Meetings on Thursdays and Fridays at 3pm)
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Harut Avagyan
Run Plan for February 19 - 22, 2016:Start close-up of the Hall at 3pm on Friday, February 19 (see "General instruction" on the right)After hall is in "Beam Permit" turn on the chicane (see "Setting up Chicane for E=2.3 GeV" under "General instructions" on the right)Establish beam to the tagger dump (see "General instruction" on the right)Bring beam to FC:
Miscellaneous Notes:
|
General Instructions:Locking up the hall on Fridays
Acceptable Beam Conditions:
Recovering from beam trips when running SVT at 0.5 mm:
Every Shift:
Every Run:
Setting up Chicane for E=2.3 GeV:Note: This requires Beam Permit and NO beam to HPS / Faraday Cup.
SVT Instructions:
ECAL Instructions:
|
|
|
|
.
Webcams:
|
Accelerator: |
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 541-7539 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |