Line 113: | Line 113: | ||
# '''Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be 50 nA. Before moving forward with 2H02A harp scans and beam profile tune, make sure orbit lock is engaged at positions on 2H00(X=0.00,Y=0.00) and on 2H02(X=-1.00,Y=-0.85). ''' | # '''Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be 50 nA. Before moving forward with 2H02A harp scans and beam profile tune, make sure orbit lock is engaged at positions on 2H00(X=0.00,Y=0.00) and on 2H02(X=-1.00,Y=-0.85). ''' | ||
# '''<font color=red> Important Note: Before bringing beams to the FC, be sure that the SVT and ECal are off, the SVT fully retracted, the target out, and the 2.82 mm SVT collimator is in. All beam studies should be done in these conditions with beam currents of 50 nA.</font>''' | # '''<font color=red> Important Note: Before bringing beams to the FC, be sure that the SVT and ECal are off, the SVT fully retracted, the target out, and the 2.82 mm SVT collimator is in. All beam studies should be done in these conditions with beam currents of 50 nA.</font>''' | ||
− | # The required beam profile at 2H02A harp is: X-width <~0.25 mm, Y-width <~ 0.10 mm, and the tilt angle <15 degrees. The spot on the Chromax viewer should be close to x=-2mm, y=-5mm. <b> Do not waste too much time on the initial beam tune, as long as rates on the halo counters are low - Downstream L/R/T/B and HPS-L/R <~few Hz/nA, and HP-SC < few x 10 Hz, the following program still can be done:</b> | + | # The required beam profile at 2H02A harp is: X-width <~0.25 mm, Y-width <~ 0.10 mm, and the tilt angle <15 degrees. The spot on the Chromax viewer should be close to x=-2mm, y=-5mm. |
+ | <!--<b> Do not waste too much time on the initial beam tune, as long as rates on the halo counters are low - Downstream L/R/T/B and HPS-L/R <~few Hz/nA, and HP-SC < few x 10 Hz, the following program still can be done:</b> --> | ||
# Set beam position | # Set beam position | ||
#* Have MCC move beam to standard values (see "General instructions" on the right) | #* Have MCC move beam to standard values (see "General instructions" on the right) |
Revision as of 10:18, 4 March 2016
[edit]
Spring 2015 Final @ 1 GeV:
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2016, 2015 |
Procedures
|
Manuals |
JLab Logbooks
|
HPS 2016 run, February 4 to March 14, Weekends Only
Shifts are manned from Friday 2pm to Monday 7am
Beam energy 2.3 GeV (1 pass)
Important: Document all your work in the logbook!
RC: Nathan Baltzell
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Harut Avakian
Run Plan for February 26 - 29, 2016:Start close-up of the Hall at 3pm on Friday, March 4
When hall reaches "Beam Permit", turn on the chicaneEstablish beam to the tagger dump
Bring beam to FC:
Miscellaneous Notes:
|
General Instructions:Locking up the hall on Fridays
Establishing Acceptable Beam Conditions:
|
Recovering from beam trips when running SVT at 0.5 mm:
| |
---|---|
Every Shift:
|
Every Run:
|
|
|
|
.
Webcams:
|
Accelerator: |
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 541-7539 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |