==General Instructions== | ==General Instructions== | ||
− | ===DAQ RECOVERY=== | + | <!--===DAQ RECOVERY=== |
If DAQ crashed/broken: | If DAQ crashed/broken: | ||
# For every daq crash login into clondaq3 as a clasrun then run the following command | # For every daq crash login into clondaq3 as a clasrun then run the following command | ||
#* clasrun@clondaq3:clasrun> <font color='blue'> save_DAQ_logs.pl</font> (See [https://logbooks.jlab.org/files/2016/04/3397123/DAQ_DPM_Crash_0.png]) | #* clasrun@clondaq3:clasrun> <font color='blue'> save_DAQ_logs.pl</font> (See [https://logbooks.jlab.org/files/2016/04/3397123/DAQ_DPM_Crash_0.png]) | ||
# [[HPS DAQ Reboot Procedure|Reboot DAQ completely.]]. | # [[HPS DAQ Reboot Procedure|Reboot DAQ completely.]]. | ||
− | # If the procedure fails to restore DAQ, call Sergey (DAQ on call) without any further disturbing the DAQ status. | + | # If the procedure fails to restore DAQ, call Sergey (DAQ on call) without any further disturbing the DAQ status.--> |
===Establishing Physics Quality Beam for HPS:=== | ===Establishing Physics Quality Beam for HPS:=== | ||
Line 174: | Line 174: | ||
#* Check the beam position on the tagger viewer, it should be approximately in the center of the screen | #* Check the beam position on the tagger viewer, it should be approximately in the center of the screen | ||
#* Follow instructions under "Procedures" on the documentation tab for "Beamline"[https://wiki.jlab.org/hps-run/images/e/e6/HPS_beamline_comm.pdf]. To tune the beam on tagger dump and perform harp scans beam current should be <10 nA. | #* Follow instructions under "Procedures" on the documentation tab for "Beamline"[https://wiki.jlab.org/hps-run/images/e/e6/HPS_beamline_comm.pdf]. To tune the beam on tagger dump and perform harp scans beam current should be <10 nA. | ||
− | #* Check profile using 2C21 and tagger harp scans, and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/3689157],[https://logbooks.jlab.org/entry/3689156]) | + | #* Check profile using 2C21 and tagger (2C24) harp scans, and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/3689157],[https://logbooks.jlab.org/entry/3689156]) |
#** Positions on both harps should be within 1mm | #** Positions on both harps should be within 1mm | ||
#** Width on 2C21 should be <~0.1+/-0.05 mm | #** Width on 2C21 should be <~0.1+/-0.05 mm | ||
#** Width on tagger harp (2C24) <~0.35 +/- 0.1mm | #** Width on tagger harp (2C24) <~0.35 +/- 0.1mm | ||
− | #* Halo counters UPS-L/R and TAG-L/T/T2 should be ~few Hz/nA [https://logbooks.jlab.org/entry/3376736] | + | <!--#* Halo counters UPS-L/R and TAG-L/T/T2 should be ~few Hz/nA [https://logbooks.jlab.org/entry/3376736]--> |
<!-- # <b> While MCC degausses the tagger magnet, verify that chicane is ON</b> | <!-- # <b> While MCC degausses the tagger magnet, verify that chicane is ON</b> | ||
#* If not, turn it on. Strictly follow the procedure in the beam line manual!--> | #* If not, turn it on. Strictly follow the procedure in the beam line manual!--> |
Revision as of 19:10, 24 June 2019
[edit]
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2019,2016, 2015HPS Upgrade ERRCOO, ESAD, RSAD Things to read before shift. |
Procedures
|
Manuals |
JLab Logbooks
|
HPS 2019 run, June X to August Y'
Beam energy 4.5 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 2pm
RC: Matt Graham
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Valery Kubarovsky
- (757) 876-1789
- 9 876-1789 from Counting Room
* !! Chicane magnets can be energized only when the hall is in Beam Permit, [1]. Chicane magnets must be off if the hall is in Restricted or in Controlled access.
Run Plan June 20 - 21, 2019
When there is stable beam:
Important Notes:
|
General InstructionsEstablishing Physics Quality Beam for HPS:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
RC daily meetings at 2 pm in the counting-house 2nd-floor conference room.
BlueJeans Info:
URL: https://bluejeans.com/794825703
Meeting ID: 794825703
|
|
|
Webcams:
|
Accelerator:
|
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 310-7198 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |