Line 121: | Line 121: | ||
<!-- * <b>Schedule and plans:</b> | <!-- * <b>Schedule and plans:</b> | ||
− | # | + | # Take production data with PROD66 (PROD67) / hps_v11_6.trg 20um target at 120 nA, HPS collimator 2.82 mm. Length of the run will be defined by the SVT bias currents, but no longer than 4 hours. |
− | + | # If peaks are visible make a log entry with the graph. | |
− | |||
# Then continue production data taking | # Then continue production data taking | ||
− | # Take random trigger data, 1 run for 300M events: PROD66 (PROD67) / hps_v6_random_30khz.trg 20um target at 120 nA, HPS collimator 2.82 mm | + | # Take random trigger data, 1 run for 300M events: PROD66 (PROD67) / hps_v6_random_30khz.trg 20um target at 120 nA, HPS collimator 2.82 mm |
− | + | # Then continue production data taking | |
− | + | # Do a beam profile check once a day, at 9 am, using 2H02 and SVT wire harps | |
− | # | + | # Take all the data! |
− | # | ||
− | |||
− | |||
==Every Shift:== | ==Every Shift:== | ||
# Follow run plan as outlined by RC | # Follow run plan as outlined by RC |
Revision as of 14:51, 29 August 2019
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2019,2016, 2015HPS Upgrade ERRCOO, ESAD, RSAD Adendum to RSAD Things to read before shift. |
Procedures
|
Manuals |
JLab Logbooks
|
HPS (E12-11-006) 2019 run, June X to August Y'
Beam energy 4.5 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 2pm
RC: Cameron Bravo
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Valery Kubarovsky
- (757) 876-1789
- 9 876-1789 from Counting Room
Important instructions
* Turn OFF beam before target move!
* No access to the alcove if the chicane magnet beacon is ON.
Chicane magnets must be OFF if the hall is in Controlled access and access to the alcove is needed or when the hall is in Restricted access. If Chicane magnets are OFF, they can be energized only when the hall is in Power or Beam Permit, [1].
* TURN OFF the chicane magnet if beam is not available due to a thunderstorm. Loss off power would seriously damage detectors.
* Fill out BTA hourly. Click "Load from EPICS" to fill the left side, then make sure numbers are correct. If needed edit the entry.
NO ABUs or BANU if beam tune is in progress, make it all BNA with ER 100%. At the end of the shift save BTA to the logbook!
* Please close any GUI that is not being used, e.g. close harp scanner after harp scan is done, close chicane, after chicane is ON, etc.
* For orbit lock positions on 2H00(X=1.0,Y=1.5) and on 2H02(X=-1.65,Y=-0.3). Use the 2.82 mm SVT collimator
Run Plan August 29 - September 3, 2019Establishing Physics Quality Beam for HPS:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
|
|
---|
RC daily meetings at 2 pm in the counting-house 2nd-floor conference room.
BlueJeans Info:
URL: https://bluejeans.com/794825703
Meeting ID: 794825703
|
|
|
Webcams:
|
Accelerator: |
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 310-7198 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5244(Shift1), 5245(Shift2) |
Hall-B Counting Room | 5247(Expert), 5502(Target) |
Hall-B Counting Room | 5246(RC1), 5126(RC2) |
Hall-B Gas Shed | 7115 |