− | - Final version of the timeline for the different stages of the design, construction, and installation of the KL beamline []. | + | - Final version of the timeline for the different stages of the design, construction, and installation of the KL beamline [https://wiki.jlab.org/klproject/images/c/c8/PAC48_schedule.xlsx]. |
- Cover_Letter draft []. | - Cover_Letter draft []. |
Revision as of 09:34, 14 May 2020
Attended: Igor.
- Supplemental materials for the PAC48 sumission:
- Final version of KLF_Analysis_ Report (hyperon case) [1]. Tex version is available at overleaf [2].
- KLF_Analysis_ Report (meson case) is coming.
- Final version of New_Equipment [3].
- Final version of the Raster document [4].
- Final version of the KFM [5]. It is available on the GlueX DB as GlueX-doc-3603 [6].
- Final version of the KPT [7].
- Final version of the CPS [8].
- Final version of the timeline for the different stages of the design, construction, and installation of the KL beamline [9].
- Cover_Letter draft [].
- The next meeting is scheduled for June 9th, 7AM [10]