<b>Attended</b>: ''Moskov'', ... ''Igor''. ''Eugene'' is on the vacation.
 
<b>Attended</b>: ''Moskov'', ... ''Igor''. ''Eugene'' is on the vacation.
 +
 +
 +
* We went succesfully through ERR-I [] and got a commettee blessing to go ahead.
  
  

Revision as of 06:43, 11 August 2023

Attended: Moskov, ... Igor. Eugene is on the vacation.


  • We went succesfully through ERR-I [] and got a commettee blessing to go ahead.


  • Tentive agenda for the KLF Collaboration meeting (September 19th [1]):
  • (10+5') Cynthia Keppel, [Welcome Remarks].
  • (20+10') Doug Higinbotham, [Summary for KLF ERR-I].
  • (15+5') Eugene Chudakov, [Hall D Status Report].
  • (15+5') Sean Dobbs, [Software for KLF].
  • (15+5') Mikhail Bashkanov, [Excited Omega baryon states at KLF].
  • (15+5') Marco Battaglieri, [Dark matter experiment in Hall D].
  • (15+5') Tim Whitlatch, [K-Long Engineering update].
  • (15+5') Hovanes Egiyan, [Conceptual design of CPS].
  • (15+5') Igor Strakovsky, [The Kaon Production target - final design].
  • (15+5') Mikhail Bashkanov, [The Flux Monitor - final design].
  • (15+5') Shukui Zhang, [Status of the CEBAF photo-injector drive laser system for KL beam].


  • KLF beam line paper for NIM.


  • On August 7th, we had a Hovanes CPS meeting discuss CPS design for Hall D and summary for CPS at ERR-I [2].


  • David Hamilton informed us that the Hall C CPS report that was submitted to lab management to get the C1 condition on E12-17-008 lifted.
  • In which case, the conceptual design report for the Hall C CPS is here (this is what we sent to Bob McKeown and was reviewed by Patrizia): [3].
  • The original experimental proposal is here: [4]. We were fully re-approved by PAC51 two weeks ago.