<b>Attended</b>: ''Moskov'', ... ''Igor''. ''Eugene'' is on the vacation.
+
<b>Attended</b>: ''Moskov'', ''Jim'', ''Mikhail'', ''Sean'', ''Justin'', ''Hivanes'', and ''Igor''. ''Eugene'' is on the vacation.
  
  

Revision as of 07:03, 11 August 2023

Attended: Moskov, Jim, Mikhail, Sean, Justin, Hivanes, and Igor. Eugene is on the vacation.


  • On August 2nd, we went succesfully through ERR-I [1] and got a commettee blessing to go ahead.


  • Speakers for the KLF Collaboration meeting (September 19th [2]):
  • (10+5') Cynthia Keppel, [Welcome Remarks].
  • (20+10') Doug Higinbotham, [Summary for KLF ERR-I].
  • (15+5') Eugene Chudakov, [Hall D Status Report].
  • (15+5') Sean Dobbs, [Software for KLF].
  • (15+5') Mikhail Bashkanov, [Excited Omega baryon states at KLF].
  • (15+5') Marco Battaglieri, [Dark matter experiment in Hall D].
  • (15+5') Tim Whitlatch, [K-Long Engineering update].
  • (15+5') Hovanes Egiyan, [Conceptual design of CPS].
  • (15+5') Igor Strakovsky, [The Kaon Production target - final design].
  • (15+5') Mikhail Bashkanov, [The Flux Monitor - final design].
  • (15+5') Shukui Zhang, [Status of the CEBAF photo-injector drive laser system for KL beam].


  • KLF beam line paper for NIM.


  • On August 7th, we had a Hovanes CPS meeting discuss CPS design for Hall D and summary for CPS at ERR-I [3].


  • David Hamilton informed us that the Hall C CPS report that was submitted to lab management to get the C1 condition on E12-17-008 lifted.
  • In which case, the conceptual design report for the Hall C CPS is here (this is what we sent to Bob McKeown and was reviewed by Patrizia): [4].
  • The original experimental proposal is here: [5]. We were fully re-approved by PAC51 two weeks ago.