Weekly Reporting

Week of December 7 - 13, 2017

Issues:

none

Accomplishments this week:

The PCs for PLC programing have been delivered. They are being setup for the remote programing test – the PLC for the cryo controls is also here. This will be done over the next week.

Safety Assessment document is still in review

The cryomodule shuffle has been done – there was a hiccup on the location of the base plates – the “C100” has a different saddle location from the original style C20/50s. These were “un-grouted” and moved back to the original position.

Waveguide hardware (nuts & bolts) have been delivered. The gallery HPA racks need to be raised 2” to accommodate the new waveguide, this design is being reviewed

Continued work on WIKI site for documentation: wiki.jlab.org/lerf