Week of November 30 – December 6, 2017

Issues:

none

Accomplishments this week:

Lab electricians have removed all of the klystrons from zone 3 and 4. They will now move to remove circulators and prepare racks for new waveguide installation.

Safety Assessment document is still in review

Waiting on personnel to do cryomodule shuffle, this is scheduled for Thursday 12/ 7

Working on a design for protecting RF cables with a “false floor” – the cables will lay on the floor between the klystron racks & the SSAs, also placed order for ~400 waveguide gaskets.

Continued work on WIKI site for documentation: wiki.jlab.org/lerf

Submitted abstract to IPAC 2018 on the LERF conversion activities