Nov 15 2017
Weekly Reporting
WBS 1.01.07 JLAB Management
Week of November 9 - 15, 2017
Issues:
Need SLAC to ship SSAs, they need BCR
Accomplishments this week:
Second design review of cryo can has been done – hope is to have bid package out before Christmas.
Notes are at: https://wiki-2015.jlab.org/lerf/index.php/Nov_13_2017_WG
Safety Assessment document is still in progress
Waveguide bid is back, we shaved off a few components – found parts in trailer & reuse more pieces for savings of ~$50k, award later this week.
3/8” Heliax order of 6,000’ is out for bid
7/8” Heliax for TLM is ordered
Waiting on personnel to do cryomodule shuffle
Continued work on WIKI site for documentation: wiki.jlab.org/lerf
Kevin visited Fermilab
Upcoming Activities:
Complete Safety Assessment document
Remove girders and two cryomodules – shuffle the third to the zone 2 position
�