(Created page with "Weekly Reporting WBS 1.01.07 JLAB Management Week of November 9 - 15, 2017 Issues: Need SLAC to ship SSAs, they need BCR Accomplishments this week: Second design revie...") |
|||
Line 5: | Line 5: | ||
Week of November 9 - 15, 2017 | Week of November 9 - 15, 2017 | ||
− | Issues: | + | ==Issues:== |
Need SLAC to ship SSAs, they need BCR | Need SLAC to ship SSAs, they need BCR | ||
− | Accomplishments this week: | + | ==Accomplishments this week:== |
Second design review of cryo can has been done – hope is to have bid package out before Christmas. | Second design review of cryo can has been done – hope is to have bid package out before Christmas. | ||
Line 29: | Line 29: | ||
Kevin visited Fermilab | Kevin visited Fermilab | ||
− | Upcoming Activities: | + | ==Upcoming Activities:== |
Complete Safety Assessment document | Complete Safety Assessment document |
Latest revision as of 09:52, 22 November 2017
Weekly Reporting
WBS 1.01.07 JLAB Management
Week of November 9 - 15, 2017
Issues:
Need SLAC to ship SSAs, they need BCR
Accomplishments this week:
Second design review of cryo can has been done – hope is to have bid package out before Christmas.
Notes are at: https://wiki-2015.jlab.org/lerf/index.php/Nov_13_2017_WG
Safety Assessment document is still in progress
Waveguide bid is back, we shaved off a few components – found parts in trailer & reuse more pieces for savings of ~$50k, award later this week.
3/8” Heliax order of 6,000’ is out for bid
7/8” Heliax for TLM is ordered
Waiting on personnel to do cryomodule shuffle
Continued work on WIKI site for documentation: wiki.jlab.org/lerf
Kevin visited Fermilab
Upcoming Activities:
Complete Safety Assessment document
Remove girders and two cryomodules – shuffle the third to the zone 2 position
�