Difference between revisions of "ATLis"
(8 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | |||
+ | 18842 - Modify LERF LCLS-II Interlock Controls | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18842] | ||
+ | |||
+ | 18823 - LERF Gun HV checkout with activated photocathode | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18823] | ||
+ | |||
+ | 18804 - LERF LLRF Firm/Software Update 2 | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18804] | ||
+ | |||
+ | 18803 - LERF LCLS-II Heater Protection Update | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18803] | ||
+ | |||
+ | 18783 - LERF LLRF Firm/Software Update | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18783] | ||
+ | |||
+ | 18770 - 30K Temp bump of LCLS-II CM in LERF Vault | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18770] | ||
+ | |||
+ | 18613 - LCLSII Transporting and Mat'l Handling | ||
+ | *[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18613] | ||
+ | |||
+ | 18537 - Move LCLS-ll cryomodule to position two | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18537] | ||
+ | |||
+ | 18346 - Air Lines LCLSII CG to Cryo Valves | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18346] | ||
+ | |||
18335 - Install Bellows Support Rail | 18335 - Install Bellows Support Rail | ||
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18335] | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18335] | ||
+ | |||
+ | 18237 - LERF Single SSA Tests | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18237] | ||
18069 - Move LCLSII Cryo Module from Test Lab to LERF Vault | 18069 - Move LCLSII Cryo Module from Test Lab to LERF Vault | ||
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18069] | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18069] | ||
+ | |||
+ | 18177 - Cable Pull LCLS2 | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/18177] | ||
18007 - LCLSII SSA/HPA raised Floor | 18007 - LCLSII SSA/HPA raised Floor | ||
Line 22: | Line 56: | ||
17841 - LCLSII SSA Delivery & Setting Material Handling Support | 17841 - LCLSII SSA Delivery & Setting Material Handling Support | ||
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17841] | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17841] | ||
+ | |||
17834 - Install LCLSII CM End Can | 17834 - Install LCLSII CM End Can | ||
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17834] | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17834] | ||
Line 99: | Line 134: | ||
17513 - LERF ODH ANNUAL CHANGE OUT 2017 | 17513 - LERF ODH ANNUAL CHANGE OUT 2017 | ||
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17513] | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17513] | ||
+ | |||
+ | 17440 - Maintenance of LERF PSS Run/safe Boxes | ||
+ | *[http://devweb.acc.jlab.org/CSUEApps/atlis/task/17440] | ||
17416 - Verify LERF Klystrons are suitable for use in 1L13 for new C50 | 17416 - Verify LERF Klystrons are suitable for use in 1L13 for new C50 |
Latest revision as of 10:51, 14 February 2019
18842 - Modify LERF LCLS-II Interlock Controls
18823 - LERF Gun HV checkout with activated photocathode
18804 - LERF LLRF Firm/Software Update 2
18803 - LERF LCLS-II Heater Protection Update
18783 - LERF LLRF Firm/Software Update
18770 - 30K Temp bump of LCLS-II CM in LERF Vault
18613 - LCLSII Transporting and Mat'l Handling
18537 - Move LCLS-ll cryomodule to position two
18346 - Air Lines LCLSII CG to Cryo Valves
18335 - Install Bellows Support Rail
18237 - LERF Single SSA Tests
18069 - Move LCLSII Cryo Module from Test Lab to LERF Vault
18177 - Cable Pull LCLS2
18007 - LCLSII SSA/HPA raised Floor
17923 - Installation of RF waveguide for two LCLS II Modules
17884 - LERF Waveguide Anchor Point Layout
17882 - Shut Down of Panel E-1000 in LERF
17881 - Alignment of FL02 LERF Cryomodule
17841 - LCLSII SSA Delivery & Setting Material Handling Support
17834 - Install LCLSII CM End Can
17831 - Install Wave Guide Supports and U-Tube Lifting Plates for LCLSII
17825 - Raise 2 Klystron Racks 2" & Install Al. Box Tube Spacers
17743 - ^LERF cryomodule shuffle
17689 - Prep FEL Girders 8F02, 8F03 and UV Happek for Removal From Beamline
17688 - Shut Down of Panel E1000 in LERF Gallery
17642 - Lerf beamline girder disconnects @ 1F02, 1F03 and 1F04
17628 - FL03 & 4 removal of HPA low level and CPS control power
17579 - Re-Assemble LERF GW Dipoles
17577 - Disconnect and Remove All Utilities From Dark Light Power Supply
17575 - Remove LERF Vault Truck Ramp Gate
17574 - Remove Dark Light Solenoid Power Lead & Cable Tray
17573 - Rework Power in LERF for New LCLS2 Project
17539 - Remove waterflow equipment from the Darklight power supply/system (LERF)
17537 - LERF Truck Ramp Shielding Block Removal
17535 - LERF UV Collimator and VUV Turning Can Removal
17533 - LERF/PSS IFIX Communication Investigation (System B)
17532 - LERF BLM Removal for Cryomodule and LCLS-II Support
17529 - Vent-up & remove beam line LERF 4F region
17528 - LERF ODH System Certification
17527 - Disconnect LERF Trim Magnets For Cryomodule Removal
17518 - Disconnect LERF bpms for Cryomodule removal
17517 - LERF WaveGuide Removal
17516 - LERF CM1F03 & 04 Removal
17514 - Secure Vacuum Cables for removal of 1F02 / 1F03 Cryomodules
17513 - LERF ODH ANNUAL CHANGE OUT 2017
17440 - Maintenance of LERF PSS Run/safe Boxes
17416 - Verify LERF Klystrons are suitable for use in 1L13 for new C50
17320 - LERF Module Drive high determination
17177 - Q0 Improvement of cryomodule by In-situ Demagnetization