Difference between revisions of "Run Meeting: Oct 25th, 2018"
Jump to navigation
Jump to search
Line 13: | Line 13: | ||
- beam studies <br /> | - beam studies <br /> | ||
- tune beam ~20:00-01:00 <br /> | - tune beam ~20:00-01:00 <br /> | ||
− | - Phase Studies | + | - Phase Studies 02:00 -... |
'''Swing shift''' | '''Swing shift''' | ||
Line 27: | Line 27: | ||
- no beam (phaser studies)<br /> | - no beam (phaser studies)<br /> | ||
− | - controlled access (~ | + | - controlled access (~08:00) <br /> |
- Jessie, Jack and Heidi entered to check LQ3 issue.<br /> | - Jessie, Jack and Heidi entered to check LQ3 issue.<br /> | ||
- Left arm restored. Right arm is powered (Dipole) low current (100 A) just to investigate its behaviour. <br /> | - Left arm restored. Right arm is powered (Dipole) low current (100 A) just to investigate its behaviour. <br /> |
Revision as of 13:47, 25 October 2018
Back to:
3:30PM Run Meeting, Counting house meeting room (200C)
RC: Carlos Ayerbe
Summary of past 24h:
Accelerator
- beam studies
- tune beam ~20:00-01:00
- Phase Studies 02:00 -...
Swing shift
- elastics runs from tune beam
Owl shift
- finish elastics
- LQ3 quench (~1:30)
Day shift
- no beam (phaser studies)
- controlled access (~08:00)
- Jessie, Jack and Heidi entered to check LQ3 issue.
- Left arm restored. Right arm is powered (Dipole) low current (100 A) just to investigate its behaviour.
- ~14:30 Hall in beam permit
Plan:
- expected beam at Swing shift.
Slides/Links
MCC scheduling Whiteboard: http://accboard.acc.jlab.org/
Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/372278653