Line 13: | Line 13: | ||
* 5th pass separator tripped a few times. | * 5th pass separator tripped a few times. | ||
* Mike took an Unser calibration. Tried BCM calibration near the noon but beam was so trippy, gave up. Will try on Saturday when we have stable beam. | * Mike took an Unser calibration. Tried BCM calibration near the noon but beam was so trippy, gave up. Will try on Saturday when we have stable beam. | ||
− | * Hall A iocs lost connection around 1:50pm, back online around 2:30pm. | + | * Hall A iocs lost connection around 1:50pm, requested an escort access to fix ups. System back online around 2:30pm. |
https://logbooks.jlab.org/entry/3555964 | https://logbooks.jlab.org/entry/3555964 | ||
+ | |||
Thanks cryo group (Robert Norton!), Radcon, Jessie, Heidi and Hall A tech team for the fast response! | Thanks cryo group (Robert Norton!), Radcon, Jessie, Heidi and Hall A tech team for the fast response! |
Latest revision as of 14:46, 6 April 2018
Back to:
4:00PM Run Meeting, Counting house meeting room (200C)
RC: Shujie Li
Status
- kin13/kin16 production in progress
- 5th pass separator tripped a few times.
- Mike took an Unser calibration. Tried BCM calibration near the noon but beam was so trippy, gave up. Will try on Saturday when we have stable beam.
- Hall A iocs lost connection around 1:50pm, requested an escort access to fix ups. System back online around 2:30pm.
https://logbooks.jlab.org/entry/3555964
Thanks cryo group (Robert Norton!), Radcon, Jessie, Heidi and Hall A tech team for the fast response!
- Hall B pass change from 3 to 5