+ | =Dec 15 Day Shift= | ||
+ | *Remove Sieve from LHRS | ||
+ | *Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz) | ||
+ | *Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz) | ||
+ | |||
+ | =Other Links= | ||
+ | |||
*'''Commissioning timetable''' [https://docs.google.com/spreadsheets/d/1LE0K4jgPMolJvvj33uXu9v-OLi_FKqjZokoChkLLNaA/edit?usp=sharing (google sheet)] | *'''Commissioning timetable''' [https://docs.google.com/spreadsheets/d/1LE0K4jgPMolJvvj33uXu9v-OLi_FKqjZokoChkLLNaA/edit?usp=sharing (google sheet)] | ||
<span>Brief but reflects the exact runplan.</span> | <span>Brief but reflects the exact runplan.</span> |
Revision as of 09:19, 15 December 2017
Dec 15 Day Shift
- Remove Sieve from LHRS
- Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
- Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
Other Links
- Commissioning timetable (google sheet)
Brief but reflects the exact runplan.
- Commissioning How-to (wiki)
Documentation and details. Could be out-of-date. Please always check with run coordinator and student experts.