Difference between revisions of "Run Plan From Run Coordinator"
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
*Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz) | *Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz) | ||
*Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz) | *Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz) | ||
− | + | '''When gas cell running is approved:''' | |
*call RC | *call RC | ||
*begin target boiling study | *begin target boiling study |
Revision as of 09:20, 15 December 2017
Dec 15 Day Shift
- Remove Sieve from LHRS
- Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
- Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
When gas cell running is approved:
- call RC
- begin target boiling study
Other Links
- Commissioning timetable (google sheet)
Brief but reflects the exact runplan.
- Commissioning How-to (wiki)
Documentation and details. Could be out-of-date. Please always check with run coordinator and student experts.