Difference between revisions of "Run Plan From Run Coordinator"
Jump to navigation
Jump to search
Line 6: | Line 6: | ||
*'''When gas cell running is approved:''' | *'''When gas cell running is approved:''' | ||
**call RC | **call RC | ||
− | **begin target boiling study | + | **begin target boiling study [https://wiki.jlab.org/tegwiki/index.php/Target_Boiling_Study] |
=Other Links= | =Other Links= |
Revision as of 10:08, 15 December 2017
Dec 15 Day Shift
- Remove Sieve from LHRS
- Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
- Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
- When gas cell running is approved:
- call RC
- begin target boiling study [1]
Other Links
- Commissioning timetable (google sheet)
Brief but reflects the exact runplan.
- Commissioning How-to (wiki)
Documentation and details. Could be out-of-date. Please always check with run coordinator and student experts.