Difference between revisions of "Run Plan From Run Coordinator"
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
*Follow Startup Procedure: https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning | *Follow Startup Procedure: https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning | ||
* HALOG EVERYTHING | * HALOG EVERYTHING | ||
− | |||
*If startup procedure is completed: | *If startup procedure is completed: | ||
− | ** | + | **Take 5uA runs, 30 min each: |
+ | ***Single-Foil Carbon, raster off | ||
+ | ***Single-Foil Carbon, raster at nominal | ||
+ | ***Multi-Foil Carbon, raster off | ||
+ | ***Multi-Foil Carbon, raster at Nominal | ||
+ | |||
=Jan 11 Swing= | =Jan 11 Swing= |
Revision as of 03:38, 12 January 2018
Jan 12 Owl
- Follow Startup Procedure: https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning
- HALOG EVERYTHING
- If startup procedure is completed:
- Take 5uA runs, 30 min each:
- Single-Foil Carbon, raster off
- Single-Foil Carbon, raster at nominal
- Multi-Foil Carbon, raster off
- Multi-Foil Carbon, raster at Nominal
- Take 5uA runs, 30 min each:
Jan 11 Swing
- Monitor the target
- Check that RHRS and LHRS are at 15.577deg and 3.1 GeV
- Take Cosmics on both arms until beam setup begins
- coordinate with MCC for 5th pass beam setup!
Dec 16 Owl Shift
- Finish the Boiling Study
- ~1am: access to move LHRS to 22deg
- Run on 3H, 3He, 1H, 2H, and empty cell until Day Shift
Dec 15 Swing Shift
- See WhiteBoard
- Boiling Study: [1]
Dec 15 Day Shift
- Remove Sieve from LHRS
- Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
- FADC threshold check
- Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
- Access begins at 1pm https://logbooks.jlab.org/entry/3505097
- When gas cell running is approved:
- call RC
- begin target boiling study [2]
Other Links
- Commissioning timetable (google sheet)
Brief but reflects the exact runplan.
- Commissioning How-to (wiki)
Documentation and details. Could be out-of-date. Please always check with run coordinator and student experts.