+ | =Jan 15 Swing / Jan 16 Owl= | ||
+ | *Carry out Kin3 plan (on whiteboard) | ||
+ | *Kin3 Plan (20.578deg, 3.1 GeV): | ||
+ | **Carbon Hole center check | ||
+ | **Dummy, 10uA, 15min | ||
+ | **Optics, 10uA, 10min | ||
+ | **Home, 20uA, 10min | ||
+ | **Carbon, 20uA, PS8=10 only!, 5min | ||
+ | **Empty, 20uA, 30min | ||
+ | **3He, 20uA, 2hr | ||
+ | **1H, 20uA, 50min | ||
+ | **2H, 20uA, 50min | ||
+ | **3H, 20uA, 1hr 40min | ||
+ | **Empty, 20uA, 30min | ||
+ | **3He, 20uA, 2hr | ||
+ | **1H, 20uA, 50min | ||
+ | **2H, 20uA, 50min | ||
+ | **3H, 20uA, 1hr 40min | ||
+ | *Call RC for spectrometer move to Kin4! | ||
+ | |||
=Jan 15 Owl= | =Jan 15 Owl= | ||
*Continue Kin2 plan from Swing shift (on whiteboard) | *Continue Kin2 plan from Swing shift (on whiteboard) |
Revision as of 21:38, 15 January 2018
Jan 15 Swing / Jan 16 Owl
- Carry out Kin3 plan (on whiteboard)
- Kin3 Plan (20.578deg, 3.1 GeV):
- Carbon Hole center check
- Dummy, 10uA, 15min
- Optics, 10uA, 10min
- Home, 20uA, 10min
- Carbon, 20uA, PS8=10 only!, 5min
- Empty, 20uA, 30min
- 3He, 20uA, 2hr
- 1H, 20uA, 50min
- 2H, 20uA, 50min
- 3H, 20uA, 1hr 40min
- Empty, 20uA, 30min
- 3He, 20uA, 2hr
- 1H, 20uA, 50min
- 2H, 20uA, 50min
- 3H, 20uA, 1hr 40min
- Call RC for spectrometer move to Kin4!
Jan 15 Owl
- Continue Kin2 plan from Swing shift (on whiteboard)
- Call RC if uncertain about anything
Jan 14 Swing
- Finish Kin1 running (see whiteboard)
- Angle change
- Call Jack a little in advance
- Set Left spectrometer to 19.135deg (TECHS ONLY, Jack will come in)
- Begin Kin2 (always use PS1=PS2=PS3=1 (unless otherwise specified))
- Carbon Hole centering check
- multifoil, 10 uA, 10 minutes
- carbon, 20 uA, 10 minutes
- carbon, 20 uA, only PS8=100, 5 minutes
- Empty Cell, 20uA, 30 minutes
- 3He Cell, 20uA, 1hr 40min
- 1H Cell, 20uA, 40min
- 2H Cell, 20uA, 40min
- 3H Cell, 1hr 20min
- Empty Cell, 20uA, 30 minutes
- 3He Cell, 20uA, 1hr 40min
- 1H Cell, 20uA, 40min
- 2H Cell, 20uA, 40min
- 3H Cell, 1hr 20min
Jan 13 Day
- Carbon Hole centering (with Meekins adjusting encoder values)
- Check distance from centered on hole to collimator edge, change only BPMBx (should be nearby in positive BPMx)
- Raster size fine tuning
- Harp scan with raster on (clock trigger only)
- BPM pedestal run (Call in Jason)
- Bullseye scan (with Jason)
- Trigger checkout (Florian looking a remote scopes)
- Prescale/deadtime checks with dummy target
- DAQ checkout (shifters/experts check online plots)
- optics data:
- Single-Foil Carbon, raster off
- Single-Foil Carbon, raster on
- Multi-Foil Carbon, raster off
- Multi-Foil Carbon, raster on
- If still waiting for gas cell permission:
- Dummy Target, 10uA, raster on
Jan 12 Swing
- Hall Access --Completed
- Collimator edge-finding --completed
- clock run for BPM sanity check
- Bogdan's raster target edge-finding sanity check
- carbon hole finding/centering (see how close we can get, may need to ask for BPMBx != BPMAx in order to avoid collimator)
- Continue with the Commissioning Plan: [1]
- Do not skip the bullseye scan (even though we took one harp scan earlier today)
- Doug will do the Arc energy measurement sometime this weekend. (Don't call him for this in the middle of the night...)
- If startup procedure is completed, take 5uA runs, 30 min each:
- Single-Foil Carbon, raster off
- Single-Foil Carbon, raster on
- Multi-Foil Carbon, raster off
- Multi-Foil Carbon, raster on
- If still waiting for gas cell permission:
- Dummy Target, 10uA, raster on
Jan 12 Owl
- Follow Startup Procedure: https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning
- HALOG EVERYTHING
- If startup procedure is completed, take 5uA runs, 30 min each:
- Single-Foil Carbon, raster off
- Single-Foil Carbon, raster at nominal
- Multi-Foil Carbon, raster off
- Multi-Foil Carbon, raster at Nominal
Jan 11 Swing
- Monitor the target
- Check that RHRS and LHRS are at 15.577deg and 3.1 GeV
- Take Cosmics on both arms until beam setup begins
- coordinate with MCC for 5th pass beam setup!
Dec 16 Owl Shift
- Finish the Boiling Study
- ~1am: access to move LHRS to 22deg
- Run on 3H, 3He, 1H, 2H, and empty cell until Day Shift
Dec 15 Swing Shift
- See WhiteBoard
- Boiling Study: [2]
Dec 15 Day Shift
- Remove Sieve from LHRS
- Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
- FADC threshold check
- Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
- Access begins at 1pm https://logbooks.jlab.org/entry/3505097
- When gas cell running is approved:
- call RC
- begin target boiling study [3]
Other Links
- Commissioning timetable (google sheet)
Brief but reflects the exact runplan.
- Commissioning How-to (wiki)
Documentation and details. Could be out-of-date. Please always check with run coordinator and student experts.