Run Meeting: April 6th, 2018

From Tritium Experiments Group
Revision as of 14:42, 6 April 2018 by Shujie (talk | contribs) (→‎Status)
Jump to navigation Jump to search

Back to:

Main Page
Daily Run Meetings

4:00PM Run Meeting, Counting house meeting room (200C)

RC: Shujie Li

(shifts)

Status

  • kin13/kin16 production in progress
  • 5th pass separator tripped a few times.
  • Mike took an Unser calibration. Tried BCM calibration near the noon but beam was so trippy, gave up. Will try on Saturday when we have stable beam.
  • Hall A iocs lost connection around 1:50pm, back online around 2:30pm.

https://logbooks.jlab.org/entry/3555964

Thanks cryo group (Robert Norton!), Radcon, Jessie, Heidi and Hall A tech team for the fast response!

  • Hall B pass change from 3 to 5

Slides


BlueJeans connection info:

To join the Meeting: https://bluejeans.com/372278653