4:00PM Run Meeting, Counting house meeting room (200C)
RC: Eric Fuchey
e'p
Smooth data taking during the last 24h. There were only minor beam issues i.e a change in the 2nd pass separator phase. Hopefully, it will go on like this and we collecting nice data over the weekend.
Beam down this morning because of injector problem (Gun HV Air Pressure Fault - bad solenoid): Total down time ~1h30.
Slides
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/372278653