Run Meeting: February 19th, 2018

From Tritium Experiments Group
Revision as of 10:07, 19 February 2018 by Efuchey (talk | contribs)
Jump to navigation Jump to search

Back to Main Page Daily_Run_Meetings

4:00PM Run Meeting, Counting house meeting room (200C)

Summary of weekend: Beam came back at the turn of swing shift on Friday. Beam had requested current, but lacked stability. We run in these conditions (variable beam stability) most of the weekend...

... until Sunday night excitment: VESDA started to give alarms around 11pm; request beam off (in case); ( + right Q1 PS had gone off, after communication went down;) -> first short access for a visual check; => smell from labyrinth, haze in the hall; -> went to controlled access for full investigation: Summary at https://logbooks.jlab.org/entry/3534243 ;


Beam taken back on Monday morning for following tasks: Work at injector to fix low energy tails RF recovery;

=> controlled access: investigate cause of yesterday's incident =>


Plan: Wait for beam back, and resume production on Kin 15 and 16.


Slides

BlueJeans connection info:

To join the Meeting: https://bluejeans.com/372278653

To join via Browser: https://bluejeans.com/372278653/browser