Difference between revisions of "BCM Calibration"

From Tritium Experiments Group
Jump to navigation Jump to search
m
Line 1: Line 1:
 
[https://wiki.jlab.org/tegwiki/index.php/Main_Page <B>Back to Tritium-Main</B>]
 
[https://wiki.jlab.org/tegwiki/index.php/Main_Page <B>Back to Tritium-Main</B>]
  
[]
+
[https://wiki.jlab.org/tegwiki/index.php/Installation_and_Commissioning <b> Back to Installation and Commissioning </b>]
  
 
(copied from GMP)
 
(copied from GMP)

Revision as of 14:48, 5 October 2017

Back to Tritium-Main

Back to Installation and Commissioning

(copied from GMP)

BCM Calibrations [2 hours] (DAY or SWING shift preferable)

Accelerator has a written procedure to follow if you wish to cross check the current at the injector with the current in the Hall.

  1. Warn MCC a few hours beforehand.
  2. The Hall A BCM and scalers need to be cross-calibrated to the Faraday cup and a BCM in the accelerator (OLO2) and the Hall A Unser. (If night shift then do NOT bother cross calibrating with the Faraday cup. You can just stay on the line with MCC and request the appropriate beam currents following the rules below.)
  3. Before beginning the procedure, make sure the Hall A BCM logger and the HRS DAQ are started, which will record the signals from all relevant BCM used during the calibration. [Here ] is how to start the logger, choose the BCM logger script (solution 2).
  4. Also start a HRS run to record the scalers during the calibration procedure, if necessary use the clock to take reasonably high data rate (above about 50 Hz at least)
  5. It is useful to have someone over in MCC to help coordinate the calibration with them.
  6. Take data on carbon target with I = 0, 3, 0, 5, 0, 7, 0, 10, 0, 15, 0, 20, 0, 25, 0, 30, 0, 40, 0, 50, 0, 60, 0, 70, 0, 80, 0 μA (or as high a current as available). Each beam period (with or without current) should last 90 s. If you get a trip during a beam up period, take 90s of beam off and restart that beam up period.