Run Plan From Run Coordinator

From Tritium Experiments Group
Revision as of 00:05, 16 December 2017 by Randallm (talk | contribs)
Jump to navigation Jump to search

Dec 16 Owl Shift

  • Finish the Boiling Study
  • ~1am: access to move LHRS to 22deg
  • Run on 3H, 3He, 1H, 2H, and empty cell until Day Shift

Dec 15 Swing Shift

  • See WhiteBoard
  • Boiling Study: [1]


Dec 15 Day Shift

  • Remove Sieve from LHRS
  • Run Dummy with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 2 million events each (~15 minutes @ 2kHz)
  • FADC threshold check
  • Run Multifoil with nominal raster at I = 22.5, 15, 10, 5, 2.5 uA -- 1 million events each (~15 minutes @ 2kHz)
  • Access begins at 1pm https://logbooks.jlab.org/entry/3505097
  • When gas cell running is approved:
    • call RC
    • begin target boiling study [2]

Other Links

Brief but reflects the exact runplan.