+ | == Meeting Info == | ||
+ | We will meet Thursday @ 10am EDT <u>'''via BlueJeans'''</u> | ||
+ | Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 | ||
+ | Phone number (for audio call in): 1-888-240-2560 | ||
+ | Meeting ID: 909497334# | ||
− | + | == Last Week's To-Do List == | |
− | + | * ME providing CAD models to look at and compare w/ 2D dimensioned layout [[media:beamlinelayoutmarch26.pdf]] | |
− | + | :: Now on [https://jeffersonlab-my.sharepoint.com/:f:/g/personal/grames_jlab_org/EhXqNtq16CBNt4JzMmy4T1ABNsJ15YGBFTQkkMenD_ommQ Link to AIPINJ OneDrive folder], then they're in the "20.03.26 Beamline Screen Shots". | |
− | + | :: MFX before A1 moves further upstream on spool | |
− | + | :: A2 is now a cube, instead of a cross | |
− | + | :: harp before A2 is rotated 45 deg CW looking downstream, there is a viewer on it too | |
− | + | * Danny working w/ MDC so their BPM shop drawings match his submitted drawing | |
− | + | :: the BPM cans from MDC are due to ship april 13th. | |
− | + | * Joe finding status of BPM feed through delivery | |
− | + | :: Requested date is 4/25 | |
− | + | :: the BPM antennae are due to ship: a quantity of 7 in three weeks, the balance on may 7th. | |
− | + | * ME working on finishing solenoid fixture designs | |
− | + | * Marcy checking on top hat configuration for Y-chamber [[media:200326_viewer shield.pdf]] | |
+ | * ME can go ahead order spools for Sections 2 & 3 | ||
+ | * Shaun add "stay clear" zone of camera to model | ||
+ | :: Joe measured 4" dia x 6" length tube | ||
+ | * Danny check with Milhous & Jlab people for dipole design | ||
+ | :: Yes, nice examples. Jay OK. Joe OK. Req submitted & signed | ||
+ | * Reza talk out with Curt or Rick about power needed and controls desired | ||
+ | * DP can, will new $$$ NEG's fit or not | ||
+ | * Marcy get quotes on A1/A2 cubes and 6-way cross w/ R-R | ||
+ | * Decide on A1 [[media:200326_aperture 1.pdf]] insert depths | ||
+ | * Finalize A2 [[media:200326_aperture 2.pdf]] in layout, need to wind coils now too | ||
+ | * Scott figure out how to control [https://vacgen.com/linear-drive-70mm-od-75mm-z-m6-tapped-stepper-encoder], set limits, positions, use encoder w/ stac5 | ||
+ | :: ordered a stac5 | ||
+ | * Let Joe Meyers know what color to paint solenoids | ||
+ | :: Lime | ||
+ | * Riad - will magnetic field of first coil reach photocathode? will it affect solenoids? | ||
+ | ::Field map: [[media:BH_Haimson_Coils.xlsx]] => Field extends to 8 cm from center of magnet. | ||
+ | * Carlos/Gabriel evaluate model for smaller gap Wien filter | ||
+ | * Lakshmi status of PSS coil models | ||
+ | * Dennis turn elegant model values into expected magnet currents. | ||
+ | :: Using the 2020-03-26 layout: [[Media:magnet_currents.ods]] | ||
+ | * Alicia show simulations of beams, evaluate layout for transmission and settings needed | ||
+ | * Joe - is the distance from MFG-A to upstream steering coil sufficient? | ||
+ | * Previous to-do list...https://wiki.jlab.org/ciswiki/index.php/March_20,_2020_-_ME/INJ/CIS |
Latest revision as of 16:15, 2 April 2020
Meeting Info
We will meet Thursday @ 10am EDT via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 909497334#
Last Week's To-Do List
- ME providing CAD models to look at and compare w/ 2D dimensioned layout media:beamlinelayoutmarch26.pdf
- Now on Link to AIPINJ OneDrive folder, then they're in the "20.03.26 Beamline Screen Shots".
- MFX before A1 moves further upstream on spool
- A2 is now a cube, instead of a cross
- harp before A2 is rotated 45 deg CW looking downstream, there is a viewer on it too
- Danny working w/ MDC so their BPM shop drawings match his submitted drawing
- the BPM cans from MDC are due to ship april 13th.
- Joe finding status of BPM feed through delivery
- Requested date is 4/25
- the BPM antennae are due to ship: a quantity of 7 in three weeks, the balance on may 7th.
- ME working on finishing solenoid fixture designs
- Marcy checking on top hat configuration for Y-chamber media:200326_viewer shield.pdf
- ME can go ahead order spools for Sections 2 & 3
- Shaun add "stay clear" zone of camera to model
- Joe measured 4" dia x 6" length tube
- Danny check with Milhous & Jlab people for dipole design
- Yes, nice examples. Jay OK. Joe OK. Req submitted & signed
- Reza talk out with Curt or Rick about power needed and controls desired
- DP can, will new $$$ NEG's fit or not
- Marcy get quotes on A1/A2 cubes and 6-way cross w/ R-R
- Decide on A1 media:200326_aperture 1.pdf insert depths
- Finalize A2 media:200326_aperture 2.pdf in layout, need to wind coils now too
- Scott figure out how to control [1], set limits, positions, use encoder w/ stac5
- ordered a stac5
- Let Joe Meyers know what color to paint solenoids
- Lime
- Riad - will magnetic field of first coil reach photocathode? will it affect solenoids?
- Field map: media:BH_Haimson_Coils.xlsx => Field extends to 8 cm from center of magnet.
- Carlos/Gabriel evaluate model for smaller gap Wien filter
- Lakshmi status of PSS coil models
- Dennis turn elegant model values into expected magnet currents.
- Using the 2020-03-26 layout: Media:magnet_currents.ods
- Alicia show simulations of beams, evaluate layout for transmission and settings needed
- Joe - is the distance from MFG-A to upstream steering coil sufficient?
- Previous to-do list...https://wiki.jlab.org/ciswiki/index.php/March_20,_2020_-_ME/INJ/CIS