Difference between revisions of "CEBAF Injector Upgrade"
Jump to navigation
Jump to search
Line 21: | Line 21: | ||
:[[A1/A2 Aperture Steering Cubes]] - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils | :[[A1/A2 Aperture Steering Cubes]] - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils | ||
:[[Injector upgrade vacuum improvements]] - Improvements in the vacuum design, use of getter and ion pumps | :[[Injector upgrade vacuum improvements]] - Improvements in the vacuum design, use of getter and ion pumps | ||
− | :[[SRF Booster | + | :[[SRF Booster]] |
==ATLIS Tasks== | ==ATLIS Tasks== |
Revision as of 13:47, 27 August 2020
This area is related to Injector Upgrade Meetings
Planning, planning, planning...
Link to AIPINJ OneDrive folder
Major Beamline Components
- DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
- FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
- PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker has been designed to operate at higher momentum and with more reliable design
- WF Wien Filters (200 kV upgrade) - Wien filters are upgraded with new coils (20 A) and new high voltage (+/- 18 kV) for operation at 200 keV
- QW Wien quadrupoles (200 kV upgrade) - New quadrouple are designed for higher 200 keV energy, but also of improved magnetic design w/ minimized dipole component
- Chopping System (200 kV upgrade)
- Pre-buncher cavity (200 kV upgrade)
- NEG coated 2.5 inch OD BPM's
- A1/A2 Aperture Steering Cubes - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils
- Injector upgrade vacuum improvements - Improvements in the vacuum design, use of getter and ion pumps
- SRF Booster
ATLIS Tasks
- AIPINJ
- PSS Injector Segment PLC Upgrade
- Injector Camac to Vme and camera upgrade
- Pedestal Location Surveys
- Install Chopper SSA's
- Chopper SSA LCW
- Penetration Drops
- Testing Wien HV Controls at UITF
- Accelerator network re-survey
- Remove and re-install BPM's Gun to chopper
- Install new IPM2I03
- Remove and calibrate current monitoring electronics
- Harp work
- RSRSRC
- New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard