Difference between revisions of "2021-07-21"
Jump to navigation
Jump to search
(2 intermediate revisions by the same user not shown) | |||
Line 36: | Line 36: | ||
# Correctors inventoried following some naming confusion (MHB vs MBH); MBH = Magnet Big Haimson (2.75" bore); MHB family will be renamed MLH = Magnet Little Haimson (1.5" bore) | # Correctors inventoried following some naming confusion (MHB vs MBH); MBH = Magnet Big Haimson (2.75" bore); MHB family will be renamed MLH = Magnet Little Haimson (1.5" bore) | ||
# Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets | # Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets | ||
+ | # Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary!) | ||
# Raster installation - [https://logbooks.jlab.org/entry/3885536 completed]; per Bill Gunning. (Thanks!) Also, thank you for software and channel access integration by Weiwei & Brian and John for staying on top of things! | # Raster installation - [https://logbooks.jlab.org/entry/3885536 completed]; per Bill Gunning. (Thanks!) Also, thank you for software and channel access integration by Weiwei & Brian and John for staying on top of things! | ||
# [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 Solenoid PS] being installed | # [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 Solenoid PS] being installed | ||
Line 44: | Line 45: | ||
# [https://logbooks.jlab.org/entry/3885781 Insertables APP undated] with new installation (Thanks Scott!); iocitf2 rebooted. | # [https://logbooks.jlab.org/entry/3885781 Insertables APP undated] with new installation (Thanks Scott!); iocitf2 rebooted. | ||
# BCM project software integration under way between Musson/Seaton and Sue Witherspoon | # BCM project software integration under way between Musson/Seaton and Sue Witherspoon | ||
+ | # Chris Norris to hook up viewers next week. | ||
+ | # Brian Freeman available for adViewer work for video camera for ITVM604A; some focusing still required. | ||
RF: | RF: | ||
# [https://logbooks.jlab.org/entry/3885411 6GHz] > 1.5GHz Down-converter installed for bunch length system | # [https://logbooks.jlab.org/entry/3885411 6GHz] > 1.5GHz Down-converter installed for bunch length system | ||
Line 58: | Line 61: | ||
# New designs for [[media:FC3-SHIELDING_20JUL21v1.pdf|FC3]] and [[media:FC4-SHIELDING_20JUL21v1.pdf|FC4]] with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction! | # New designs for [[media:FC3-SHIELDING_20JUL21v1.pdf|FC3]] and [[media:FC4-SHIELDING_20JUL21v1.pdf|FC4]] with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction! | ||
# [[media:JL0029599-2000UITF_MeV_BEAMLINE07-JUN-21.pdf|Songsheet]] being updated by Shaun; be sure to let him know when changes are made! | # [[media:JL0029599-2000UITF_MeV_BEAMLINE07-JUN-21.pdf|Songsheet]] being updated by Shaun; be sure to let him know when changes are made! | ||
+ | # Status of permanent shielding purchase? | ||
Experiment: | Experiment: | ||
# [[media:ESAD_UITF-irradiation beamline_071421.docx|ESAD]], [[media:COO-UITF-irradiation-exp_070921.docx|COO]], and draft response to ERR under way by Gigi. ESAD/COO signed and turned over to Accelerator DSO. | # [[media:ESAD_UITF-irradiation beamline_071421.docx|ESAD]], [[media:COO-UITF-irradiation-exp_070921.docx|COO]], and draft response to ERR under way by Gigi. ESAD/COO signed and turned over to Accelerator DSO. | ||
Line 63: | Line 67: | ||
* EES work happening in earnest | * EES work happening in earnest | ||
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | * [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | ||
− | |||
− | |||
− | |||
<u>Still to do:</u> | <u>Still to do:</u> |
Latest revision as of 09:22, 21 July 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
- To join via phone, use one of the following numbers and the Conference ID: 984025598.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- 7/26/21 Start Hot Check-out
New items for discussion:
Short term schedule update:
This week:
Reports by Group: CIS/EGG:
- Gun/Depo chamber bake started and completed
- Gun HVPS tank topped to 60 psig SF6; NF3 charged as well
- R30 resistor installed for gun HV processing
- Gun anode picoammeter connected
- Decarad probes placed for gun
- MDSK201 interlock in gun HVPS bypassed for HV commissioning (See ABIL5170)
- Steel puck in place
- Gun HV Processing under way (UITFList 1663); up to 182kV so far
- Gun rebuild schedule
DC Power:
- Corrector installation & cable reroute mostly complete, turned over to DC power
- Correctors inventoried following some naming confusion (MHB vs MBH); MBH = Magnet Big Haimson (2.75" bore); MHB family will be renamed MLH = Magnet Little Haimson (1.5" bore)
- Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets
- Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary!)
- Raster installation - completed; per Bill Gunning. (Thanks!) Also, thank you for software and channel access integration by Weiwei & Brian and John for staying on top of things!
- Solenoid PS being installed
Instrumentation and Controls:
- BPMs connections good - save iocipmm904 removal - iocipmm901 installed in its place
- BPM IOCs updated with new configuration. (Thanks Kyle!)
- Install target mechanism (Completed), motor controls tested - Survey required
- Insertables APP undated with new installation (Thanks Scott!); iocitf2 rebooted.
- BCM project software integration under way between Musson/Seaton and Sue Witherspoon
- Chris Norris to hook up viewers next week.
- Brian Freeman available for adViewer work for video camera for ITVM604A; some focusing still required.
RF:
- 6GHz > 1.5GHz Down-converter installed for bunch length system
Vacuum:
SSG:
- BLM locations being set 7/21 following this meeting
- FSD inputs for magnet and BCM being prepared
ME / Installation:
- Nomenclature for elements disseminated and labelled
- Build 80/20 support structure for Pb (Completed)
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. 80/20 reworked for support
- Pb stacked; RCG required modification due to permanent shielding req delay.
- New designs for FC3 and FC4 with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction!
- Songsheet being updated by Shaun; be sure to let him know when changes are made!
- Status of permanent shielding purchase?
Experiment:
- ESAD, COO, and draft response to ERR under way by Gigi. ESAD/COO signed and turned over to Accelerator DSO.
Other:
- EES work happening in earnest
- List of Engineering Jobs remaining
Still to do:
- Add Mu metal over bellows on wastewater line.
Next Week:
- Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Engineering work on beam line starting
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan) Strawman