Difference between revisions of "Wednesday May 14, 2014"
Jump to navigation
Jump to search
(9 intermediate revisions by 2 users not shown) | |||
Line 9: | Line 9: | ||
1- Bubble Chamber progress at Argonne | 1- Bubble Chamber progress at Argonne | ||
− | 2- | + | 2- Electron line status |
− | :: Layout [[media: | + | :: Layout [[media:140514_BubbleLayout.pdf]] |
− | |||
− | |||
:: Radiator [[media:140513_Radiator.pdf]] | :: Radiator [[media:140513_Radiator.pdf]] | ||
− | + | ||
− | + | 3- Schedule | |
− | + | ||
− | + | : Planning meetings | |
− | + | :: reviews | |
− | :: | + | :: install kick-off |
− | + | :: commissioning plan | |
− | + | ||
− | + | : Electron Line | |
− | + | :: dismantle 5D | |
− | + | :: fab/buy/build | |
− | + | :: install | |
− | + | :: controls | |
− | + | :: checkout | |
− | + | ||
− | + | : Prep work for chamber | |
− | * Bubble | + | :: tunnel resources |
− | ** | + | :: service building resources |
− | ** | + | :: control room resources |
− | ** | + | |
− | ** | + | : Install of chamber |
− | * | + | :: ship estimate |
+ | :: install/checkout goals | ||
+ | :: commissioning/test goals | ||
+ | |||
+ | |||
+ | |||
+ | ---- | ||
+ | |||
+ | '''Notes from this meeting:''' | ||
+ | |||
+ | * Bubble Chamber is ready to be filled with N<sub>2</sub>O. | ||
+ | * Once ready, all safety documents must be forwarded to D. Meekins. | ||
+ | * The chamber will be shipped with mercury in place but not N<sub>2</sub>O. | ||
+ | |||
+ | |||
+ | * Magnet dipole is signed off and out for bids. | ||
+ | * The Hall Probe has arrived at JLab. | ||
+ | * Magnet Alignment Fixture is being fabricated by the Machine Shop. | ||
+ | |||
+ | |||
+ | * The collimator table and holders will be made of aluminum. | ||
+ | * The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed. | ||
+ | * Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...). | ||
+ | |||
+ | |||
+ | * Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): [[media:JLab_sketch.pdf]] [[media:JLab_sketch.pptx]] |
Latest revision as of 12:34, 20 May 2014
We will meet in TL 2236 on Wednesday May 14 at 3:30 pm EST.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 4402297, followed by “#”
Agenda:
1- Bubble Chamber progress at Argonne
2- Electron line status
- Layout media:140514_BubbleLayout.pdf
- Radiator media:140513_Radiator.pdf
3- Schedule
- Planning meetings
- reviews
- install kick-off
- commissioning plan
- Electron Line
- dismantle 5D
- fab/buy/build
- install
- controls
- checkout
- Prep work for chamber
- tunnel resources
- service building resources
- control room resources
- Install of chamber
- ship estimate
- install/checkout goals
- commissioning/test goals
Notes from this meeting:
- Bubble Chamber is ready to be filled with N2O.
- Once ready, all safety documents must be forwarded to D. Meekins.
- The chamber will be shipped with mercury in place but not N2O.
- Magnet dipole is signed off and out for bids.
- The Hall Probe has arrived at JLab.
- Magnet Alignment Fixture is being fabricated by the Machine Shop.
- The collimator table and holders will be made of aluminum.
- The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed.
- Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...).
- Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): media:JLab_sketch.pdf media:JLab_sketch.pptx