Difference between revisions of "Wednesday May 14, 2014"

From Ciswikidb
Jump to navigation Jump to search
 
(3 intermediate revisions by the same user not shown)
Line 44: Line 44:
 
'''Notes from this meeting:'''
 
'''Notes from this meeting:'''
  
* Bubble Chamber is ready to be filled with N2O
+
* Bubble Chamber is ready to be filled with N<sub>2</sub>O.
* Once ready, all safety documents must be forwarded to D. Meekins
+
* Once ready, all safety documents must be forwarded to D. Meekins.
* The chamber will be shipped with mercury in place but not N2O
+
* The chamber will be shipped with mercury in place but not N<sub>2</sub>O.
  
* Magnet dipole is signed off and out for bids
 
* The Hall Probes has arrived at JLab
 
* Magnet Alignment Fixture is being fabricated by the Machine Shop
 
  
* The collimator table and holders will be made of aluminum
+
* Magnet dipole is signed off and out for bids.
* The table should be wide enough to stack copper bricks to shield the back scattered gammas if needed
+
* The Hall Probe has arrived at JLab.
* Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...)
+
* Magnet Alignment Fixture is being fabricated by the Machine Shop.
  
* Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC):
+
 
 +
* The collimator table and holders will be made of aluminum.
 +
* The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed.
 +
* Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...).
 +
 
 +
 
 +
* Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): [[media:JLab_sketch.pdf]] [[media:JLab_sketch.pptx]]

Latest revision as of 12:34, 20 May 2014

We will meet in TL 2236 on Wednesday May 14 at 3:30 pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 4402297, followed by “#”

Agenda:

1- Bubble Chamber progress at Argonne

2- Electron line status

Layout media:140514_BubbleLayout.pdf
Radiator media:140513_Radiator.pdf

3- Schedule

Planning meetings
reviews
install kick-off
commissioning plan
Electron Line
dismantle 5D
fab/buy/build
install
controls
checkout
Prep work for chamber
tunnel resources
service building resources
control room resources
Install of chamber
ship estimate
install/checkout goals
commissioning/test goals



Notes from this meeting:

  • Bubble Chamber is ready to be filled with N2O.
  • Once ready, all safety documents must be forwarded to D. Meekins.
  • The chamber will be shipped with mercury in place but not N2O.


  • Magnet dipole is signed off and out for bids.
  • The Hall Probe has arrived at JLab.
  • Magnet Alignment Fixture is being fabricated by the Machine Shop.


  • The collimator table and holders will be made of aluminum.
  • The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed.
  • Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...).