'''Notes from this meeting:''' | '''Notes from this meeting:''' | ||
− | * Bubble Chamber is ready to be filled with | + | * Bubble Chamber is ready to be filled with N<sub>2</sub>O. |
− | * Once ready, all safety documents must be forwarded to D. Meekins | + | * Once ready, all safety documents must be forwarded to D. Meekins. |
− | * The chamber will be shipped with mercury in place but not | + | * The chamber will be shipped with mercury in place but not N<sub>2</sub>O. |
− | * Magnet dipole is signed off and out for bids | + | * Magnet dipole is signed off and out for bids. |
− | * The Hall | + | * The Hall Probe has arrived at JLab. |
− | * Magnet Alignment Fixture is being fabricated by the Machine Shop | + | * Magnet Alignment Fixture is being fabricated by the Machine Shop. |
− | * The collimator table and holders will be made of aluminum | + | * The collimator table and holders will be made of aluminum. |
− | * The table should be wide enough to stack copper bricks to shield the back scattered gammas if needed | + | * The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed. |
− | * Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...) | + | * Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...). |
− | * Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): | + | * Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): [[media:JLab_sketch.pdf]] [[media:JLab_sketch.pptx]] |
Latest revision as of 12:34, 20 May 2014
We will meet in TL 2236 on Wednesday May 14 at 3:30 pm EST.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 4402297, followed by “#”
Agenda:
1- Bubble Chamber progress at Argonne
2- Electron line status
- Layout media:140514_BubbleLayout.pdf
- Radiator media:140513_Radiator.pdf
3- Schedule
- Planning meetings
- reviews
- install kick-off
- commissioning plan
- Electron Line
- dismantle 5D
- fab/buy/build
- install
- controls
- checkout
- Prep work for chamber
- tunnel resources
- service building resources
- control room resources
- Install of chamber
- ship estimate
- install/checkout goals
- commissioning/test goals
Notes from this meeting:
- Bubble Chamber is ready to be filled with N2O.
- Once ready, all safety documents must be forwarded to D. Meekins.
- The chamber will be shipped with mercury in place but not N2O.
- Magnet dipole is signed off and out for bids.
- The Hall Probe has arrived at JLab.
- Magnet Alignment Fixture is being fabricated by the Machine Shop.
- The collimator table and holders will be made of aluminum.
- The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed.
- Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...).
- Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): media:JLab_sketch.pdf media:JLab_sketch.pptx