Difference between revisions of "Meeting 9/29/22 - COMTRA"
Jump to navigation
Jump to search
(3 intermediate revisions by 2 users not shown) | |||
Line 8: | Line 8: | ||
* Quick Reference v.16 [[media:UITF_quick_reference_rev.16.pdf]] | * Quick Reference v.16 [[media:UITF_quick_reference_rev.16.pdf]] | ||
* UED List Version 4 [[media:comptra_beamline_v4.xlsx]] | * UED List Version 4 [[media:comptra_beamline_v4.xlsx]] | ||
− | |||
* [[UITF Fall 2022 Schedule]] | * [[UITF Fall 2022 Schedule]] | ||
− | * Steps to align x-ray beam | + | * Steps to align x-ray beam, install collimator/magnet/detector [[media:220920_Table_Steps_v2.pptx]] |
* Recent installation photos with UED names [[media:220914_COMTRA.pptx]] | * Recent installation photos with UED names [[media:220914_COMTRA.pptx]] | ||
== Readiness Updates == | == Readiness Updates == | ||
+ | * Beam Setup | ||
+ | ** keV/MeV setup before detector installed [[media:220929_COMTRA_JOE.docx]] | ||
+ | ** Run Plan Version 5 [[media:COMTRA-RunPlan-v5.xlsx]] | ||
+ | |||
* ME/Layout | * ME/Layout | ||
** Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut) | ** Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut) | ||
Line 19: | Line 22: | ||
* Experiment components | * Experiment components | ||
** magnet measurement => done | ** magnet measurement => done | ||
+ | ** Eric is building the detector => today and tomorrow | ||
* I&C jobs | * I&C jobs | ||
Line 29: | Line 33: | ||
** Helicity generator => tested, ready | ** Helicity generator => tested, ready | ||
** High Voltage => tested, ready | ** High Voltage => tested, ready | ||
− | ** EFADC | + | ** DAQ cabling => done |
− | ** Kepco PS | + | ** EFADC data and analysis => trying to run at 78 kHz |
+ | ** Kepco PS => status? | ||
== Older Links== | == Older Links== |
Latest revision as of 07:36, 29 September 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
Experiment Time!!!
- UITF logbook => https://logbooks.jlab.org/book/uitflog
- UITF Compton Transmission Polarimeter Data Acquisition System
- Quick Reference v.16 media:UITF_quick_reference_rev.16.pdf
- UED List Version 4 media:comptra_beamline_v4.xlsx
- UITF Fall 2022 Schedule
- Steps to align x-ray beam, install collimator/magnet/detector media:220920_Table_Steps_v2.pptx
- Recent installation photos with UED names media:220914_COMTRA.pptx
Readiness Updates
- Beam Setup
- keV/MeV setup before detector installed media:220929_COMTRA_JOE.docx
- Run Plan Version 5 media:COMTRA-RunPlan-v5.xlsx
- ME/Layout
- Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)
- Experiment components
- magnet measurement => done
- Eric is building the detector => today and tomorrow
- I&C jobs
- Pull 6 fibers from DAQ to mezzanine => done
- Align x-ray camera for x-ray card after collimator => done
- Insertable 1/2-waveplate => done
- No DAC output from BCM Receiver => Chad is working on it
- DAQ/Controls
- Helicity generator => tested, ready
- High Voltage => tested, ready
- DAQ cabling => done
- EFADC data and analysis => trying to run at 78 kHz
- Kepco PS => status?
Older Links
- UITFList Links
- General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
- DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
- Beamline
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
- Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
- Detector
- Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint