Difference between revisions of "Meeting 9/29/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
 
(One intermediate revision by the same user not shown)
Line 8: Line 8:
 
* Quick Reference v.16 [[media:UITF_quick_reference_rev.16.pdf]]
 
* Quick Reference v.16 [[media:UITF_quick_reference_rev.16.pdf]]
 
* UED List Version 4 [[media:comptra_beamline_v4.xlsx]]
 
* UED List Version 4 [[media:comptra_beamline_v4.xlsx]]
* Run Plan Version 5 [[media:COMTRA-RunPlan-v5.xlsx]]
 
 
* [[UITF Fall 2022 Schedule]]
 
* [[UITF Fall 2022 Schedule]]
* Steps to align x-ray beam
+
* Steps to align x-ray beam, install collimator/magnet/detector [[media:220920_Table_Steps_v2.pptx]]
 
* Recent installation photos with UED names [[media:220914_COMTRA.pptx]]
 
* Recent installation photos with UED names [[media:220914_COMTRA.pptx]]
  
 
== Readiness Updates ==
 
== Readiness Updates ==
 +
* Beam Setup
 +
** keV/MeV setup before detector installed [[media:220929_COMTRA_JOE.docx]]
 +
** Run Plan Version 5 [[media:COMTRA-RunPlan-v5.xlsx]]
 +
 
* ME/Layout
 
* ME/Layout
 
** Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)
 
** Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)

Latest revision as of 07:36, 29 September 2022

Thursday's @ 9am EDT by Zoom

Experiment Time!!!

Readiness Updates

  • ME/Layout
    • Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)
  • Experiment components
    • magnet measurement => done
    • Eric is building the detector => today and tomorrow
  • I&C jobs
    • Pull 6 fibers from DAQ to mezzanine => done
    • Align x-ray camera for x-ray card after collimator => done
    • Insertable 1/2-waveplate => done
    • No DAC output from BCM Receiver => Chad is working on it
  • DAQ/Controls
    • Helicity generator => tested, ready
    • High Voltage => tested, ready
    • DAQ cabling => done
    • EFADC data and analysis => trying to run at 78 kHz
    • Kepco PS => status?