Difference between revisions of "Meeting 9/1/22 - COMTRA"
Jump to navigation
Jump to search
Line 6: | Line 6: | ||
* General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371 | * General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371 | ||
* DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370 | * DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370 | ||
+ | * COMTRA run time | ||
+ | ** UITFlist => https://tasklists.jlab.org/uitflist/tasks/107600 | ||
+ | |||
=== Last Week's Action Items === | === Last Week's Action Items === |
Latest revision as of 12:50, 3 October 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
New UITFList entries
- General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
- DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
- COMTRA run time
- UITFlist => https://tasklists.jlab.org/uitflist/tasks/107600
Last Week's Action Items
- Magnet to-do's
- One complete magnet on-site
- QA's beginning at MMF
- Nick's to-do's
- One KEPCO installed UITF, another being installed at MMF for checkout
- Install/cable dummy load next week
- ME to-do's
- extend spool and support two locations => https://mis.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331199&code=1
- layout modifications for lead wall with hole => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331187&code=11
- stand => Chris G. points Thu/Fri, then Ricky/Bern
- lead bricks => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331188&code=11
- top of stand w/ rails/alignment ??
- Vac to-do's
- Move pump cart, vent line
- Remove/stow wastewater Ti window + fast valve gauge
- Add/support spool - reducer - ceramic - dump
- Pump down
- DAQ to-do's
- cables pulled
- heliax connectors done
- PMT connectors ...?
- DAQ in mech room, ready for the network....
- Riad - coordinate with Bryan/Hai for 4 usec integration testing, implement for Mott, forward detector studies
- Detector hut to-do's
- Assemble BGO/PMT into detector chassis
- install/instrument collimator + magnet + detector, then rough alignment for check out
- Prepare for commissioning (collimator, x-ray card, camera), but not magnet nor detector box
- Greg's to-do's
- compute integrated asymmetry
- use slurm to run jobs on farm
- simulate 5 configurations
DAQ
- DAQ install at UITF media:220817_DAQ_PREP.pptx
Beamline
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Stands PR Shop Job
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
Detector
- Bases - due 9/15 - comes with Thi in September
- Collimator - (2) on-hand media:JL0015777_Cu_collimator.pdf thumb
- Absorbers - (6) on-hand media:Absorber - 240 D 001 14_V4.pdf thumb
- Boxes - (2) on hand thumb
- BGO - (2) on-hand thumb thumb thumb thumb thumb
- PMT and mu shields - (4) on-hand thumb
Geant4 Model
Action Items
Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint