Difference between revisions of "Wednesday June 11, 2014"
Jump to navigation
Jump to search
Line 25: | Line 25: | ||
'''Notes from this meeting:''' | '''Notes from this meeting:''' | ||
− | * PAC41 listed the Bubble Chamber as a ''High Impact'' | + | * PAC41 listed the Bubble Chamber as a ''High Impact'' experiment. |
* Bubble Chamber is filled with N<sub>2</sub>O. | * Bubble Chamber is filled with N<sub>2</sub>O. | ||
− | + | * Dave and Brad will decide on who and where the collimator will be built. The design is complete and the drawing is ready. | |
+ | * | ||
Revision as of 15:01, 12 June 2014
We will meet in TL 2236 on Wednesday June 11 at 3:30 pm EST.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 4402297, followed by “#”
Agenda:
1 - Bubble Chamber progress at Argonne
2 - (Grames) Beam line progress at JLab:
- * Coordination meeting (May 28) media:140527_BubbleInstallKickoff.pptx media:140527_BubbleInstallKickoff.pdf
- * Review final girder components
- Assembly media:JL0015130 COLLIMATOR TABLE ASSEMBLY.pdf
- Radiator media:JL0015733 CU RADIATOR WINDOW ASSY.pdf
- Collimator media:JL0015777 CU COLLIMATOR.pdf
- * BPM bench top calibration using Goubau surface wave transmission line (G-line) technique
3 - (All) How to proceed with readiness review (beam line, safety, radiological, commissioning plan, ?) so the beam line is ready for commissioning at the end of summer ?
Notes from this meeting:
- PAC41 listed the Bubble Chamber as a High Impact experiment.
- Bubble Chamber is filled with N2O.
- Dave and Brad will decide on who and where the collimator will be built. The design is complete and the drawing is ready.
- Rolf and Arne will decide on the exact framework of the Bubble Chamber Readiness Review but expected to be exactly like PEPPo:
- Conduct of Operations (COO)
- Experiment Safety Assessment Document (ESAD)
- Radiation Safety Assessment Document (RSAD)
- Beamline Review
- Bubble Chamber Safety Review:
- Pressure System
- Mercury
- Laughing Gas
- Operational Safety Procedure (OSP)