Meeting 8/18/22 - COMTRA
Jump to navigation
Jump to search
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
Installation
- Cleaning area has begun, lasts another week or so... then installation jobs could start
Layout
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Stands PR Shop Job
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
Detector
- Collimator - (2) on-hand media:JL0015777_Cu_collimator.pdf thumb
- Absorbers - (6) on-hand media:Absorber - 240 D 001 14_V4.pdf thumb
- Boxes - (2) on hand thumb
- BGO - (2) on-hand thumb thumb thumb thumb thumb
- PMT and mu shields - (4) on-hand thumb
- Bases - due 9/15 - comes with Thi in September
DAQ
- DAQ install at UITF media:220817_DAQ_PREP.pptx
Geant4 Model
Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint