Difference between revisions of "April 6, 2016 - Monthly 4-laser Upgrade Status Meeting"

From Ciswikidb
Jump to navigation Jump to search
Line 8: Line 8:
  
 
=== SCAM-II (Roger) ===
 
=== SCAM-II (Roger) ===
* Requirements document
+
* March
 +
** Additional input from Kevin Jordan and Michael Tiefenback collected.
 +
** Grames met with Injector group, solicited pre-draft input
 +
** March 31st - Version 1 draft circulated [[media:SAMII_v1.docx]] to Flood, Hansknecht, Robertson, Higgins
 +
* April
 +
** Hansknecht and Robertson provided feedback
 +
** Flood/Grames reviewed feedback
 +
* April 5th - Version 2 draft [[media:SAMII_v2.docx]] circulated to larger group for review
 +
 
  
 
=== LLRF (Tomasz) ===
 
=== LLRF (Tomasz) ===
 
* Implementation timeline
 
* Implementation timeline

Revision as of 12:08, 5 April 2016

We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.

Schedule (Joe)

Laser Status (John)

  • Status

SCAM-II (Roger)

  • March
    • Additional input from Kevin Jordan and Michael Tiefenback collected.
    • Grames met with Injector group, solicited pre-draft input
    • March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
  • April
    • Hansknecht and Robertson provided feedback
    • Flood/Grames reviewed feedback
  • April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review


LLRF (Tomasz)

  • Implementation timeline