April 6, 2016 - Monthly 4-laser Upgrade Status Meeting

From Ciswikidb
Jump to navigation Jump to search

We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.

Schedule (Joe)

  • Summer SAD
    • Apr 06 - Apr 27 : Halls A/B/D
    • Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
    • May 13 - Jun 27 : PRAD / Bubble runs
    • Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
    • Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
    • Aug 19 - Sep 1 : Bubble Run II
    • Sep 2 - 20 : PSS Cert
    • Oct 1 : Fall Run Begins

Laser Status (John)

  • Status

SCAM-II (Roger)

  • March
    • Additional input from Kevin Jordan and Michael Tiefenback collected.
    • Grames met with Injector group, solicited pre-draft input
    • March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
  • April
    • Hansknecht and Robertson provided feedback
    • Flood/Grames reviewed feedback and refined document punch list
    • April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review

LLRF (Tomasz)