Difference between revisions of "Wednesday June 11, 2014"

From Ciswikidb
Jump to navigation Jump to search
Line 13: Line 13:
 
: * Final Girder
 
: * Final Girder
 
:: Assembly [[media:JL0015130 COLLIMATOR TABLE ASSEMBLY.pdf]]
 
:: Assembly [[media:JL0015130 COLLIMATOR TABLE ASSEMBLY.pdf]]
:: Radiator  [[media:JL0015733_prelim]]
+
:: Radiator  [[media:JL0015733 CU RADIATOR WINDOW ASSY.pdf]]
:: Collimator [[media:JL0015777_prelim]]
+
:: Collimator [[media:JL0015777 CU COLLIMATOR.pdf]]
 
: * BPM bench calibration
 
: * BPM bench calibration
  
 
3 - (All) How to proceed with readiness review (beam line, safety, radiological, commissioning plan, ?) so the beam line is ready for commissioning at the end of summer ?
 
3 - (All) How to proceed with readiness review (beam line, safety, radiological, commissioning plan, ?) so the beam line is ready for commissioning at the end of summer ?

Revision as of 15:07, 11 June 2014

We will meet in TL 2236 on Wednesday June 11 at 3:30 pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 4402297, followed by “#”

Agenda:

1 - Bubble Chamber progress at Argonne

2 - (Grames) Beam line progress at JLAB

* Coordination meeting (May 28) media:140527_BubbleInstallKickoff.pptx media:140527_BubbleInstallKickoff.pdf
* Final Girder
Assembly media:JL0015130 COLLIMATOR TABLE ASSEMBLY.pdf
Radiator media:JL0015733 CU RADIATOR WINDOW ASSY.pdf
Collimator media:JL0015777 CU COLLIMATOR.pdf
* BPM bench calibration

3 - (All) How to proceed with readiness review (beam line, safety, radiological, commissioning plan, ?) so the beam line is ready for commissioning at the end of summer ?