Difference between revisions of "KPP Run"
Jump to navigation
Jump to search
Line 97: | Line 97: | ||
== Establish beam to the tagger yoke dump == | == Establish beam to the tagger yoke dump == | ||
# Work with MCC to establish beam on the tagger yoke dump - <b>This is the first time we are running to this new dump, record everything, rates in some of halo counters can be away off the chart. Consult with RC if you see something very unusual. </b> | # Work with MCC to establish beam on the tagger yoke dump - <b>This is the first time we are running to this new dump, record everything, rates in some of halo counters can be away off the chart. Consult with RC if you see something very unusual. </b> | ||
− | # See [[Media:CLAS12_beamline_commissioning.pdf|Beamline Commissioning Plans]] for details, execute 2(a) to 2(g). | + | # See [[Media:CLAS12_beamline_commissioning.pdf|Beamline Commissioning Plans]] for details, execute 2(a) to 2(g). <b> Note, MCC may use up to 4 uA tune mode beam for short time periods for steering purposes </b>. |
# Log every harp scan | # Log every harp scan | ||
# Log Main scaler GUI every time conditions change | # Log Main scaler GUI every time conditions change |
Revision as of 19:02, 2 February 2017
[edit]
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 KPP run, February 3 to March 3
Beam energy 6.4 GeV (3 pass)
Important: Document all your work in the logbook!
RC: Stepan Stepanyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
Run Plan for February 2 - 3, 2017 :Start close-up of the Hall at 5pm on Thursday, February 2Locking up the hall on Fridays
Establish beam to the tagger yoke dump
Bring beam to FC:
At this point call DAQ, EC, DC, and FTOF experts, notify them that beam is ready for data taking
Important Notes:
|
General Instructions:Establishing Acceptable Beam Conditions:
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
Webcams |