Difference between revisions of "KPP Run"
Jump to navigation
Jump to search
Line 81: | Line 81: | ||
== <font color=blue>''' Run Plan for February 2 - 3, 2017 : '''</font>== | == <font color=blue>''' Run Plan for February 2 - 3, 2017 : '''</font>== | ||
− | == | + | == The Hall was closed and brought to controlled access at 8pm on Thursday, February 2 == |
− | === Locking up the hall | + | |
− | + | === Locking up the hall === | |
* Work with the hall work coordinator (Doug Tilles or his designee) to make sure hall is ready for sweep at around 3pm: | * Work with the hall work coordinator (Doug Tilles or his designee) to make sure hall is ready for sweep at around 3pm: | ||
** Vacuum is good, magnet power supplies (Tagger and Torus) are turned ON and in remote mode, LCW is on. | ** Vacuum is good, magnet power supplies (Tagger and Torus) are turned ON and in remote mode, LCW is on. | ||
Line 89: | Line 89: | ||
* When ready notify MCC to start sweep and lockup of the hall. | * When ready notify MCC to start sweep and lockup of the hall. | ||
* Make sure all necessary monitoring GUIs are up and running. | * Make sure all necessary monitoring GUIs are up and running. | ||
− | * Make sure beam viewer screens are up. | + | * Make sure beam viewer screens are up. |
− | * When hall | + | * When hall is in "Beam Permit" |
** Ramp torus to 10% of max current (380A) | ** Ramp torus to 10% of max current (380A) | ||
** Turn all beamline devices ON, turn all CLAS12 detectors OFF | ** Turn all beamline devices ON, turn all CLAS12 detectors OFF |
Revision as of 20:55, 2 February 2017
[edit]
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 KPP run, February 3 to March 3
Beam energy 6.4 GeV (3 pass)
Important: Document all your work in the logbook!
RC: Stepan Stepanyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Eugene Pasyuk
- (757) 876-1789
- 9 876-1789 from Counting Room
Run Plan for February 2 - 3, 2017 :The Hall was closed and brought to controlled access at 8pm on Thursday, February 2Locking up the hall
Establish beam to the tagger yoke dump
Bring beam to FC:
At this point call DAQ, EC, DC, and FTOF experts, notify them that beam is ready for data taking
Important Notes:
|
General Instructions:DAQ RECOVERYIf DAQ crashed/broken: call DAQ on-call cell phone. Establishing Acceptable Beam Conditions:
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
Webcams |
Manuals |