Difference between revisions of "Run Group D"
Line 70: | Line 70: | ||
</center> | </center> | ||
− | == RC: | + | == RC: TBD == |
* (757) 575-7540 | * (757) 575-7540 | ||
* 9 575 7540 from Counting Room | * 9 575 7540 from Counting Room | ||
Line 82: | Line 82: | ||
<br> | <br> | ||
− | + | == <font color=blue>''' Run Plan: '''</font>== | |
+ | |||
+ | |||
+ | * Initial RG-D plan with the '''Hall-B nuclear target assembly''': | ||
+ | |||
+ | |||
+ | [[File:CLAS12_targetassembly.png|thumb|left|150px|upright=0.45|Sliced Target's Assembly inside the Solenoid]] [[File:RGD-E_plan1.png|thumb|none|center|700px|upright=0.45]] | ||
+ | |||
+ | |||
+ | * Initial RG-E plan with the '''dual USM target''' setup: | ||
− | | | + | [[File:RGD-E_plan2.png|thumb|none|center|550px|upright=0.45]] |
− | |||
+ | {| {{TableStyle1}} | ||
+ | | valign=top width=50% | | ||
== <font color=blue>''' References and Standards:'''</font>== | == <font color=blue>''' References and Standards:'''</font>== | ||
− | |||
<b> Restoration of Beam to Hall B</b> | <b> Restoration of Beam to Hall B</b> | ||
Line 125: | Line 134: | ||
==<font color=blue>''' General Instructions''':</font>== | ==<font color=blue>''' General Instructions''':</font>== | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
'''Every Shift:''' | '''Every Shift:''' | ||
Line 149: | Line 152: | ||
* Fill out the run info in [https://docs.google.com/spreadsheets/d/1NY1GNIZXPtpB9u4QwP6eNRSrvDkCzFmhQg5RR3V3j7E/edit#gid=0 run list] at the beginning and at the end of each run. | * Fill out the run info in [https://docs.google.com/spreadsheets/d/1NY1GNIZXPtpB9u4QwP6eNRSrvDkCzFmhQg5RR3V3j7E/edit#gid=0 run list] at the beginning and at the end of each run. | ||
* Compare the monitoring histograms from clas12mon to the reference and troubleshoot as needed. <b> When checking the ECAL response, make sure to look at the histograms for each sector by using the sector buttons at the bottom of the clas12mon window - if adcecal* or/and adcpcal* ROC crashes, there will be no alarm and the histograms are the way to notice this issue. </b> | * Compare the monitoring histograms from clas12mon to the reference and troubleshoot as needed. <b> When checking the ECAL response, make sure to look at the histograms for each sector by using the sector buttons at the bottom of the clas12mon window - if adcecal* or/and adcpcal* ROC crashes, there will be no alarm and the histograms are the way to notice this issue. </b> | ||
+ | |||
+ | |||
+ | * ''The main lights in the Hall (dome lights) and the Forward Carriage lights are being kept off because of light leaks affecting some of the detectors. If these lights are switched on during an access, they should be switched off when leaving the Hall. Note that the dome lights when switched off cannot be turned back on immediately because they require 10-15 min to cooldown.'' | ||
+ | * ''Turn DC HV off only for beam tuning; if no beam is available or when beam is stable, keep them on even if you are not taking data.'' | ||
+ | * ''In case of loss of communication with IOCBTARG, follow instructions at https://logbooks.jlab.org/entry/3502218'' | ||
+ | * ''With any issue contact On-Call Experts or RC - do not spend more than 15-20 min trying to fix the problem.'' | ||
+ | * ''Check for and read any comments to log-book entries made during your shift.'' | ||
|} | |} |
Revision as of 00:05, 6 March 2019
- Shift Documentation
- Phone Numbers
- Short Term Schedule
- Monitoring
- Calibration/Coordination
- Useful Links
Shift ScheduleShift ChecklistHot CheckoutBeam Time Accounting |
Manuals
|
Procedures |
JLab Logbooks
|
|
|
- Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
- To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
- Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.
Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.
CLAS12 Run Group D+E, Spring 2021
Beam energy 11 GeV (50 pass)
Important: Document all your work in the logbook!
Remember to fill in the run list at the beginning and end of each run (clas12run@gmail.com can fill the run list)
RC: TBD
- (757) 575-7540
- 9 575 7540 from Counting Room
- rc@jlab.org
PDL: Nathan Baltzell
- (757) 876-1789
- 9 876-1789 from Counting Room
- baltzell@jlab.org
Run Plan:
- Initial RG-D plan with the Hall-B nuclear target assembly:
- Initial RG-E plan with the dual USM target setup:
References and Standards:Restoration of Beam to Hall B Nominal Beam Positions
FSD Thresholds
Reference Harp Scans for Beam on Tagger Dump: 2C21 [1], 2C24 [2] Reference Harp Scans for Beam on Faraday Cup: 2C21 [3], 2C24 [4], 2H01 [5] Reference Monitoring Histograms (20 nA, production trigger) [6] Reference Monitoring Histograms (35 nA, production trigger) [7] Reference Scalers and Halo-Counter Rates:
SVT acceptable currents: <10 nA (typically < 1 nA) with no beam and no HV; ~< 400 nA (HV ON, no beam); 10 nA [19], 20 nA [20], 30 nA [21], 40 nA [22], 50 nA [23], 60 nA [24], 75 nA [25]
|
General Instructions:Every Shift:
Every Run:
|
- Note 1: Be very mindful of the background rates in the halo counters, rates in the detectors, and currents in the SVT for all settings to ensure that they are at safe levels.
The integrated rates on the upstream counters have to be in the range 0-15 Hz (rates up 100 Hz are acceptable) and the rates on the midstream counters have to be in the range 10-20 Hz (acceptable up to 50 Hz) @50 nA. Counting rates in the range of hundreds of Hz may indicate bad beam tune or bleed-through from other Halls.
- Note 2: At the end of each run, follow the standard DAQ restart sequence
"end run", "cancel", "reset", then if the run ended correctly, "download", "prestart", "go". If the run did not end correctly or if any ROCs had to be rebooted, "configure", "download", "prestart", "go".
After each step, make sure it is complete in the Run Control message window. If a ROC has crashed, find which one it is and issue a roc_reboot command and try again. Contact the DAQ expert if there are any questions.
- Note 3: FTOF HVs: The goal is to minimize the number of power cycles of the dividers.
- should be turned off during the initial beam tuning down to the Faraday Cup after CLAS12 has been off for a long shutdown, when doing a Moller run, when doing harp scans, or if there is tuned/pulsed beam in the upstream beamline.
- should be left on after an initial beam tune has been established and if there are only minor steering adjustments and “tweaks” being made.
- if shift workers have doubts what to do with the HVs, they can always contact the TOF on-call expert for advice.
- Note 4: In case of a Torus and/or Solenoid Fast Dump do the following:
- Notify MCC to request beam OFF and to drop Hall B status to Power Permit
- Call Engineering on-call
- Make separate log entry with copies to HBTORUS and HBSOLENOID logbooks. In the "Notify" field add Ruben Fair, Probir Goshal, Dave Kashy and esr-users@jlab.org
- Notify Run Coordinator
- Turn off all detectors
- Note 5: When beam is being delivered to the Faraday Cup:
- the Fast Shut Down elements: Upstream, Midstream, Downstream, BOM, and Solenoid should always be in the state UNMASKED
- No changes to the FSD threshold should be made without RC or beamline expert approval
- Note 6: Any request for a special run or change of configuration has to be approved by the RC & documented
- Note 7: Carefully check the BTA every hour and run the script btaGet.py to print for you what HAS TO BE in BTA for this hour. Edit BTA if it is incorrect.
- Note 8: Reset CLAS12MON frequently to avoid histogram saturation.
- Note 9: Shift workers must check the occupancies! Use this tool to compare to previous runs: [26]
- Note 10 Do not Turn OFF MVT HV: Instead go to 'Restore settings' from the MVT overview screen:
- SafeMode.snp for beam tuning and Moeller runs
- MV_HV_FullField.snp for full solenoid field
- MV_HV_MidField.snp wgeb solenoid < 4T
- NOTE 11 Check the vacuum periodically, make sure vacuum id not higher than 5e-5
- NOTE 12 Always reset the CFD threshold after all power off/on on the CND CAMAC crate
After the CAMAC crate (camac1) holding the CND CFD boards is switched off for any reason, it is mandatory to reset the associated thresholds typing the following command from any clon machine terminal: $CODA/src/rol/Linux_x86_64/bin/cnd_cfd_thresh -w 0
If this command is failing and the crate is not responding, reboot it as follows: roc_reboot camac1
- NOTE 13 Shift workers should anyway check routinely scalers to verify they update correctly and make a logbook entry if anomalies are observed after starting a new run.
- NOTE 14: To solve common SVT issues see https://logbooks.jlab.org/entry/3615766
- NOTE 15: After any reboot of crate 'adcband1', reboot tdcband1 crate to avoid sync problems of TDCs.
- NOTE 16: For RICH recovery procedures, please see Log entry https://logbooks.jlab.org/entry/3562273. This would apply in the cases of 1. DAQ crash: rich4 is not responding or 2. RICH alarms (LV,missing tile, temperature etc). If it does not work or you are uncertain about what to do, contact the RICH expert on call. Please, note that missing tiles typically occur due to lost communication. Keep in mind that the recovery procedure will kill DAQ. If DAQ is running for other purpose, rather than data taking (for which the RICH acceptance would be important) do not initiate the recovery procedure.
- The most critical parameter for RICH is the temperature of the photosensors. If the temperature rises above limits, an interlock will automatically turn the RICH HV and LV. If this happens, notify the expert on call and keep taking data without RICH.
Webcams |
Manuals |
Epics on the web
|
General Info
- RG-D analysis coordinator: L. El Fassi
- RG-E analysis coordinator: W. Amstrong
- Cooking Chief: A. El Alaoui
CALIBRATIONS FOR RG-D & E
- Documentation and executables of the various calibration suites are on the CalCom wiki page [27]
- Initial Calibration Volunteered:
- DC: S. Nanda
- FTOF: J. Carvajal
- CTOF: J. Carvajal
- ECAL/PCAL: T. Chetry
- HTCC: I. Illari
- LTCC: M. Ungaro
- RICH: H.S. Jo
- RF: Patrick Moran (RGB ?)