Line 105: Line 105:
  
 
* ''' Tuesday, day shift. Random trigger runs @10 nA and 50nA '''
 
* ''' Tuesday, day shift. Random trigger runs @10 nA and 50nA '''
** Ask to take  beam away
+
''' DONE '''
** Motors-Blocker -> GO HOME (out of the beam)
 
** Ask beam current = 10 nA
 
** Download from scratch rgb_v9_1_faraday_noprescale.trg
 
** Take data 2 hours
 
 
 
** Ask beam current = 50 nA
 
** Download from scratch rgb_v9_1_faraday_prescale-3.trg
 
** Take data 2o minutes, NOT MORE.
 
 
 
** Ask to tak beam away
 
** Motors-Blocker -> GO BEAM
 
** Ask beam current = 50 nA
 
** Download from scratch rgb_v10.trg
 
** Take production data
 
 
 
 
* ''' Wednesday, Moller Run after RF recovery (swing shift) '''
 
* ''' Wednesday, Moller Run after RF recovery (swing shift) '''
  

Revision as of 15:35, 19 March 2019

[edit]

Shift Schedule

Shift Checklist

Hot Checkout

Beam Time Accounting

Manuals

Procedures

JLab Logbooks

RC schedule

  • Jan 26 - Feb 6: S. Niccolai
  • Feb 6 - Feb 13: Y. Ilieva
  • Feb 13 - Feb 20: S. Stepanyan
  • Feb 20 - Feb 27: F. Hauenstein
  • Feb 27 - Mar 6: S. Niccolai
  • Mar 6 to Mar 12: J. Gilfoyle
  • Mar 12 to Mar 20: V. Kubarowsky
  • Mar 20 to Mar 25: S. Stepanyan


Clas12design.png